Clay v AJ Crump and Sons Ltd: CA 1964

An architect, a demolition contractor and a building contractor were each held liable to an employee of building contractors for the collapse of a wall which, with the architect’s approval, demolition contractors had left standing.
Held: As far as tests for causation were concerned each case must be tested on its own facts and there was no general rule.
If an architect or engineer designs a house or a bridge so negligently that it falls down, he is liable to every one of those who are injured in the fall.

Judges:

Upjohn LJ

Citations:

[1964] 1 QB 533

Jurisdiction:

England and Wales

Citing:

AppliedStapley v Gypsum Mines Ltd HL 25-Jun-1953
Plaintiff to take own responsibility for damage
The question was whether the fault of the deceased’s fellow workman, they both having disobeyed their foreman’s instructions, was to be regarded as having contributed to the accident.
Held: A plaintiff must ‘share in the responsibility for the . .

Cited by:

CitedBinod Sutradhar v Natural Environment Research Council CA 20-Feb-2004
The defendant council had carried out research into a water supply in India in the 1980s. The claimant drank the water, and claimed damages for having consumed arsenic in it.
Held: There is a close link between the tests in law for proximity . .
CitedGray v Fire Alarm Fabrication Services Ltd and others QBD 3-Mar-2006
The deceased, a maintenance engineer died after falling through a skylight at work. The court considered the respective liabilities of his employer and the landowner. . .
CitedSutradhar v Natural Environment Research Council HL 5-Jul-2006
Preliminary Report of Risk – No Duty of Care
The claimant sought damages after suffering injury after the creation of water supplies which were polluted with arsenic. He said that a report had identified the risks. The defendant said that the report was preliminary only and could not found a . .
Lists of cited by and citing cases may be incomplete.

Professional Negligence, Construction

Updated: 09 May 2022; Ref: scu.194627

Erith Contractors Limited v Costain Civil Engineering Limited: 1994

The meaning and effect of clause 18(2) was considered.
Held: It was axiomatic that if the contractor requires the sub-contract dispute to be dealt with jointly with the main contract dispute with the employer in accordance with the provisions of clause 66 of the main contract, he is under an obligation to take the necessary steps to have the two disputes dealt with in accordance with clause 66.

Judges:

His Honour John Lloyd Q.C

Citations:

[1994] ADRLJ 123

Jurisdiction:

England and Wales

Cited by:

CitedLafarge Redlands Aggregates Limited (Formerly Redland Aggregates Limited) v Shephard Hill Civil Engineering Limited HL 27-Jul-2000
Once a main contractor chose, under the standard form contract, to have his dispute with one sub-contractor referred to arbitration as part of another dispute with a different contractor, he should complete the procedure within a reasonable time. It . .
Lists of cited by and citing cases may be incomplete.

Contract, Construction

Updated: 09 May 2022; Ref: scu.191138

M J Gleeson Group Plc v Wyatt of Snetterton Limited: CA 1994

The Court rejected a sub-contractor’s argument that a dispute between the main contractor and the employer within the meaning of clause 18(2) can only arise when clause 66 is invoked. The word ‘dispute’ in clause 18(2) must be given its ordinary meaning which prima facie comprehends the case where a claim has been put forward and rejected. Clause 18(2) was capable of causing serious financial difficulties for sub-contractors, but it was not for the court to rewrite the sub-contract in order to substitute its judgment of what was commercially fair between the parties.

Judges:

Steyn L.J

Citations:

[1994] 72 BLR

Statutes:

ICE Standard Form (1979)

Jurisdiction:

England and Wales

Cited by:

CitedLafarge Redlands Aggregates Limited (Formerly Redland Aggregates Limited) v Shephard Hill Civil Engineering Limited HL 27-Jul-2000
Once a main contractor chose, under the standard form contract, to have his dispute with one sub-contractor referred to arbitration as part of another dispute with a different contractor, he should complete the procedure within a reasonable time. It . .
Lists of cited by and citing cases may be incomplete.

Construction

Updated: 09 May 2022; Ref: scu.191139

Panamena Europea Navigacion v Frederick Leyland and Co: HL 1947

The parties had entered into an agreement providing for arbitration of any disputes. Lord Thankerton said: ‘By entering into the contract the respondents agreed that the appellant’s surveyor should discharge both these duties and therefore they cannot claim that the appellant’s surveyor must be in the position of an independent arbitrator, who has no other duty which involves acting in the interests of one of the parties.’
and ‘Dr Telfer declined to proceed with the matter unless he was provided with the information to which, on his erroneous view of the contract, he held himself entitled; in this view the Appellants concurred, and this position was maintained up to and after the issue of the writ. This means an illegitimate condition precedent to any consideration of the granting of a certificate was insisted on by Dr. Telfer and by the Appellants. It is almost unnecessary to cite authority to establish that such conduct on the Appellants’ part absolved the Respondents from the necessity of obtaining such a certificate, and that the Respondents are entitled to recover the amount claimed in the action.’
and ‘The view of the function of the appellant surveyor under clause 7 of the contract which I have already expressed, makes it clear beyond dispute that the Respondents have done everything which was necessary for them to do in order to require Dr. Telfer to proceed to consider the granting of a certificate under clause 7, but that Dr. Telfer declined to proceed with the matter unless he was provided with the information to which, on his erroneous view of the contract, he held himself entitled; in this view the Appellants concurred, and this position was maintained up to and after the issue of the writ. This means an illegitimate condition precedent to any consideration of the granting of a certificate was insisted on by Dr. Telfer and by the Appellants. It is almost unnecessary to cite authority to establish that such conduct on the Appellants’ part absolved the Respondents from the necessity of obtaining such a certificate, and that the Respondents are entitled to recover the amount claimed in the action.’

Judges:

Lord Thankerton

Citations:

[1947] AC 428

Jurisdiction:

England and Wales

Citing:

Appeal fromLeyland and Co v Cia Panamena Europea Navigacion CA 1943
Goddard LJ said: ‘He, therefore, was unwilling to carry out the duty assigned by the contract to him. The defendants either were of the same opinion or adopted his view; for this purpose, it matters not which. Consequently, they neither required him . .

Cited by:

CitedAMEC Mining v Scottish Coal Company SCS 6-Aug-2003
The pursuers contracted to remove coal by opencast mining from the defender’s land. They said the contract assumed the removal first of substantial peat depositys from the surface by a third party. They had to do that themselves at substantial cost. . .
AppliedHounslow London Borough Council v Twickenham Gardens Development Limited 1971
The defendant, a building contractor, had been allowed into occupation of a site owned by the plaintiff council under a building contract. The council had sought to determine the contract by notice under its terms. The contractor refused to vacate . .
CitedAmec Civil Engineering Ltd v Secretary of State for Transport CA 17-Mar-2005
The contractors appealed a decision that an arbitrator had jurisdiction to hear a claim against them in respect of works carried out on the Thelwall viaduct. The contractors denied that there had been a dispute which could found a reference, and no . .
Lists of cited by and citing cases may be incomplete.

Construction, Arbitration

Updated: 09 May 2022; Ref: scu.185452

W Lamb Limited (Trading As The Premier Pump and Tank Company) v J Jarvis and Sons Plc: TCC 31 Jul 1998

Contractors built a petrol station, and sub-contractors the underground piping. Leaks developed, and it was agreed to complete repairs, and apportion financial repairs through the court proceedings. In a case where a judge found it difficult to apportion blame, he could return to rely upon the question of onus. The parties had not alleged contributory negligence, and no apportionment could be made under the Act. There had been no sufficient agreement as to apportionment to prevent the judge reading it as necessary to give it business sense. Where there was multiple causation of damage, it was appropriate to distribute responsibility accordingly.
Court Service The Plaintiff, as sub-contractor to the Defendant, installed the pipework for a petrol filling station. The Defendant was responsible for the concrete supporting and surrounding the pipework. The pipework developed leaks and had to be replaced. The parties had agreed that the replacement works be carried out, reserving their positions as to the expense, for which each sought to make the other liable. The current trial was of liability only. In substance the only issue was whether the pipes failed because of faulty workmanship by the Plaintiff or because of the acts or omissions of the Defendant.
Held: (i) the failure was caused equally by the defaults of the Plaintiff and the Defendant; (ii) there was no rule of law which prevented effect from being given to that finding; (iii) the Defendant should pay one third of the Plaintiff’s costs of the trial.

Judges:

Judge Hicks QC

Citations:

[1998] EWHC Technology 304

Links:

Bailii

Statutes:

Civil Liability (Contributions) Act 1978

Jurisdiction:

England and Wales

Citing:

CitedMorris v London Iron and Steel Co Ltd CA 1987
In exceptional cases, a judge conscientiously seeking to decide the issues between the parties might have to conclude ‘I just do not know’. . .
CitedTennant Radiant Heat Ltd v Warrington Development Corporation 1988
A property comprised a large building let on fully repairing leases of 22 units. The many rain outlets were allowed to become blocked, and water accumulated above one unit before that part of the roof collapsed. The landlord appealed a finding that . .
Lists of cited by and citing cases may be incomplete.

Construction, Evidence, Damages

Updated: 09 May 2022; Ref: scu.135885

Barry Urquart Associates (a firm) v East Surrey Health Authority: CA 22 Jan 2002

A health authority appointed the claimant to begin work designing a new hospital. The hospital was completed by the defendant successor authority who had appointed a different firm of architects to complete the work. The claimant appealed a dismissal of its claim for the costs of the initial work undertaken.
Held: The contact failed to include any clause entitling payment for the initial works. Earlier papers suggesting this might happen had not been incorporated into the contract.

Judges:

Lord Justice Latham, Mr Justice Wilson

Citations:

Gazette 01-Feb-2002

Jurisdiction:

England and Wales

Construction, Contract

Updated: 08 May 2022; Ref: scu.167556

G W Atkins Ltd v Scott: CA 1980

A building owner complained of defective tiling installed by the appellant. He claimed the cost of retiling the whole roof. The county court judge found that the tiling was defective, but that the defects were mostly cosmetic and of a minor character. He refused to give the plaintiff the cost of reinstatement, but awarded instead the sum of andpound;250 as damages for bad workmanship. The defects as not being very serious, and accordingly that it would be unreasonable to go to the expense of completely stripping the tiles.
Held: The appeal failed.
Sir David Cairns said that the judge’s finding that it would be unreasonable to award the cost of reinstatement was not open to attack on appeal: ‘[Counsel for the defendant] accepts that in some cases it would be grossly unreasonable, or capricious, or perverse, to suggest reinstatement and that in such a case some other basis of assessment must be found. I confess that I can see no reason in principle, nor any support in the authorities, for the proposition that the test is other than lack of reasonableness simpliciter . .’
Ackner LJ said: ‘I accept that the court must have some regard for the predilections of the building owner, but that is only one of the factors. To take a wholly fanciful example; the half round tiles at the edge of the bath . . were white. They did not match the tiles as they should have done. If, for the purpose of this argument, they could only have been removed and replaced by the removal of all the tiles in the bathroom at a cost of several hundred pounds, would it have been reasonable for the plaintiff to have required this to be done? [Counsel for the defendant] contends that his client is entitled to say, ‘I want what I bargained for. What you have done is unacceptable to me.’ Such an approach seems to me to make his client the sole arbiter of what is ‘reasonable.”
Stephenson LJ agreed with both judgments.

Judges:

Stephenson LJ, Ackner LJ, Sir David Cairns

Citations:

(1980) 7 Const LJ 215

Jurisdiction:

England and Wales

Cited by:

CitedRuxley Electronics and Construction Ltd v Forsyth HL 29-Jun-1995
Damages on Construction not as Agreed
The appellant had contracted to build a swimming pool for the respondent, but, after agreeing to alter the specification to construct it to a certain depth, in fact built it to the original lesser depth, Damages had been awarded to the house owner . .
Lists of cited by and citing cases may be incomplete.

Construction, Damages

Updated: 08 May 2022; Ref: scu.526103

Walter Wardle v The Very Reverend John Bethune: PC 20 Nov 1871

Article 1688 of the Civil Code of Lower Canada enacts that, ‘I If a building perish in the whole or in part within ten years, from a defect in construction, or even from the unfavourable nature of the ground, the Architect superintending the work and the Builder are jointly and severally liable for the loss.’ Such Article held to be declaratory of the law of Lower Canada, as it existed before the promulgation of the Code. A Builder, before the passing of the Code, contracted to execute, in a workmanlike manner, all the work requisite to be done in building and completing Christ Church Cathedral, in Lower Canada, according to the plans and drawings made by an Architect, upon foundations already made and completed by a previous Builder, under the direction of his Employer’s Architect, the expense of which foundations the contract stipulated should be estimated and allowed for. The Builder erected the Cathedral in strict conformity with the contract, under the direction of the Architect, and in a workmanlike manner; but the Tower of the Cathedral, shortly after it was erected, and before the works were completed, sunk, and considerable damage was done. The cause of the sinking was found to be the insufficiency of the foundations, as planned by the original Architect, and constructed by the former Builder. This defect, though not patent, might have been discovered by the Builder of the Cathedral, before making the contract : Held (affirming the judgment of the Court of Queen’s Bench to Lower Canada), in an action by the Builder against his employer (the Employer claiming to deduct from the contract price agreed to be paid to the Builder, the amount of his charge for repairing the damages caused to the building by the sinking of the Tower, through the insufficiency of the foundations) that the Employer was entitled to make the deduction, as the Builder was responsible for the defect in the foundations, and was not freed from liability either by acting under the directions of his Employer’s Architect, or by reason of the defective foundations being the work of the preceding Builder. The decision in the case of Brown v. Laurie adopted.

Citations:

[1871] EngR 46, (1871) 8 Moo PC NS 223, (1871) 17 ER 296

Links:

Commonlii

Construction, Commonwealth

Updated: 05 May 2022; Ref: scu.280227

London Borough of Merton v Leach: 1985

The defendant agreed to construct 287 dwellings for the plaintiff. There were disputes on various matters and an arbitration took place. Eleven issues were appealed.
Held: There was an implied term that the plaintiff would not hinder the defendant in its performance, and that the parties would do what they could to achieve performance. The plaintiff’s architect in particular was obliged to supply accurate specifications.

Judges:

Vinelott J

Citations:

(1985) 32 BLR 51

Jurisdiction:

England and Wales

Cited by:

CitedPersimmon Homes (South Coast) Ltd v Hall Aggregates (South Coast) Ltd and Another TCC 10-Oct-2008
The parties had agreed for the sale of land under an option agreement. The builder purchasers now sought to exercise rights to adjust the price downwards.
Held: The provisions had been intended and had achieved a prompt and binding settlement . .
Lists of cited by and citing cases may be incomplete.

Construction

Updated: 05 May 2022; Ref: scu.277769

William Tompkinson and Sons Ltd v St Michaels Parochial Church Council: 1990

Judges:

Judge Stannard

Citations:

[1990] CLJ 319

Jurisdiction:

England and Wales

Cited by:

CitedPearce and High Ltd v Baxter and Another CA 24-Mar-1999
The clause in JCT specifying procedures for claiming against contractors did not oust the employers’ common law rights. An employer failing to give notice under the defects liability clause in time, could still sue under common law for the defect. . .
Lists of cited by and citing cases may be incomplete.

Construction

Updated: 05 May 2022; Ref: scu.277768

Clark Contracts v The Burrell Co (Construction Management) Ltd (Second Debate): ScSf 1 Oct 2002

Judges:

Sheriff J.A. Taylor

Citations:

2002 SLT 103

Links:

ScotC

Statutes:

Housing Grants, Construction and Regeneration Act 1996 111

Jurisdiction:

Scotland

Cited by:

CitedRupert Morgan Building Services (LLC) Ltd v Jervis and Jervis CA 12-Nov-2003
The defendants had engaged the claimants under standard form clauses for construction work. They issued a notice to withold payment, but out of time.
Held: The section required the notice to be given with the prescribed period. The risk of the . .
Lists of cited by and citing cases may be incomplete.

Construction

Updated: 05 May 2022; Ref: scu.182021

Blaenau Gwent Borough Council v Sabz Ali Khan: CA 4 May 1993

A land-owner is liable for work he has ordered to be carried out on his property. The ‘person carrying out the work under the regulations may not be the person or only the person who physically does the work.

Citations:

Times 04-May-1993

Statutes:

Building Regulations 1985 (1985 No 1065) 14(3)

Jurisdiction:

England and Wales

Health and Safety, Construction

Updated: 05 May 2022; Ref: scu.78441

Trollope and Colls Limited and Holland, Hannen and Cubitts Ltd, trading as Nuclear Civil Contractors (a firm) v The Atomic Power Construction Ltd: 1962

It is possible for a construction contract to have retrospective effect, in a situation where work has commenced before any contractual relationship has been entered into between the parties involved.

Citations:

[1962] 3 All E R 1936

Jurisdiction:

England and Wales

Construction

Updated: 04 May 2022; Ref: scu.241560

Imodco Ltd v Wimpey Major Projects Ltd: CA 1987

Glidewell LJ stated that the cost of work to put pipes in the position contracted for would be recoverable if there was an intention to carry out the work and if it was reasonable so to do.

Judges:

Glidewell LJ

Citations:

(1987) 40 BLR 1

Cited by:

CitedRuxley Electronics and Construction Ltd v Forsyth HL 29-Jun-1995
Damages on Construction not as Agreed
The appellant had contracted to build a swimming pool for the respondent, but, after agreeing to alter the specification to construct it to a certain depth, in fact built it to the original lesser depth, Damages had been awarded to the house owner . .
Lists of cited by and citing cases may be incomplete.

Construction, Damages

Updated: 04 May 2022; Ref: scu.526099

Minscombe Properties Ltd v Sir Alfred McAlpine and Sons Ltd: CA 1986

O’Connor LJ applied the test of reasonableness in determining whether the cost of reinstatement of land to its contracted for condition should be recoverable as damages.

Judges:

O’Connor LJ

Citations:

(1986) 2 Const LJ 303

Jurisdiction:

England and Wales

Cited by:

CitedRuxley Electronics and Construction Ltd v Forsyth HL 29-Jun-1995
Damages on Construction not as Agreed
The appellant had contracted to build a swimming pool for the respondent, but, after agreeing to alter the specification to construct it to a certain depth, in fact built it to the original lesser depth, Damages had been awarded to the house owner . .
Lists of cited by and citing cases may be incomplete.

Construction, Damages

Updated: 04 May 2022; Ref: scu.526100

Bellgrove v Eldridge: 1954

High Court of Australia. The builder built a house with defective foundations, as a result of which the house was unstable. The building owner brought an action against the builder claiming the cost of reinstatement.
Held: His claim succeeded on the facts.
The court approved the rule as stated in Hudson on Building Contracts that: ‘The measure of the damages recoverable by the building owner for the breach of a building contract is . . the difference between the contract price of the work or building contracted for and the cost of making the work or building conform to the contract’ as to the case law: ‘In none of these cases is anything more done than that work which is required to achieve conformity and the cost of the work, whether it be necessary to replace only a small part, or a substantial part, or, indeed, the whole of the building is, subject to the qualification which we have already mentioned and to which we shall refer, together with any appropriate consequential damages, the extent of the building owner’s loss. The qualification, however, to which this rule is subject is that, not only must the work undertaken be necessary to produce conformity, but that also, it must be a reasonable course to adopt.’
The cost of reinstatement work subject to the qualification of reasonableness was the extent of the loss. Reasonableness was a factor to be considered in determining what was that loss rather than, as had been argued, merely a factor in determining which of two alternative remedies were appropriate for a loss once established.
The land owner, having contracted for a building, is, as a general rule, entitled to have a building which conforms with the contract plans, the High Court continued: ‘The qualification, however, to which this rule is subject is that, not only must the work undertaken be necessary to produce conformity, but that also, it must be a reasonable course to adopt. No one would doubt that where pursuant to a building contract calling for the erection of a house with cement rendered external walls of second-hand bricks, the builder has constructed the walls of new bricks of first quality the owner would not be entitled to the cost of demolishing the walls and re-erecting them in second-hand bricks. In such circumstances the work of demolition and re-erection would be quite unreasonable or it would, to use a term current in the United States, constitute ‘economic waste’ . . We prefer, however, to think that the building owner’s right to undertake remedial works at the expense of a builder is not subject to any limit other than is to be found in the expressions ‘necessary’ and ‘reasonable’, for the expression ‘economic waste’ appears to us to go too far and would deny to a building owner the right to demolish a structure which, though satisfactory as a structure of a particular type, is quite different in character from that called for by the contract. Many examples may, of course, be given of remedial work, which though necessary to produce conformity would not constitute a reasonable method of dealing with the situation and in such cases the true measure of the building owner’s loss will be the diminution in value, if any, produced by the departure from the plans and specifications or by the defective workmanship or materials. As to what remedial work is both ‘necessary’ and ‘reasonable’ in any particular case is a question of fact.’

Citations:

(1954) 90 CLR 613

Cited by:

CitedRuxley Electronics and Construction Ltd v Forsyth HL 29-Jun-1995
Damages on Construction not as Agreed
The appellant had contracted to build a swimming pool for the respondent, but, after agreeing to alter the specification to construct it to a certain depth, in fact built it to the original lesser depth, Damages had been awarded to the house owner . .
Lists of cited by and citing cases may be incomplete.

Damages, Commonwealth, Construction

Updated: 04 May 2022; Ref: scu.526101

Wolverhampton Corporation v Emmons: 1901

The court granted an order for specific performance of a covenant in a building contract. Romer LJ said that the first condition for specific enforcement of a building contract was that ‘the particulars of the work are so far definitely ascertained that the court can sufficiently see what is the exact nature of the work of which it is asked to order the performance’.

Judges:

Romer LJ

Citations:

[1901] 1 QB 515

Cited by:

CitedCo-Operative Insurance Society Ltd v Argyll Stores HL 21-May-1997
The tenants of a unit on a large shopping centre found the business losing money, and closed it in contravention of a ‘keep open’ clause in the lease. They now appealed from a mandatory injunction requiring them to keep the store open.
Held: . .
Lists of cited by and citing cases may be incomplete.

Land, Construction

Updated: 01 May 2022; Ref: scu.247893

C R Taylor (Wholesale) Ltd v Hepworths Ltd: 1977

May J referred with approval to a statement in McGregor On Damages (13th edn, 1972) paras 1059-1061 that in deciding between diminution in value and cost of reinstatement the appropriate test was the reasonableness of the plaintiffs desire to reinstate the property and remarked that the damages to be awarded were to be reasonable as between plaintiff and defendant. He concluded that in the case before him to award the notional cost of reinstatement would be unreasonable since it would put the plaintiffs in a far better financial position then they would have been before the fire occurred.

Judges:

May J

Citations:

[1977] 1 WLR 659, [1977] 2 All ER 784

Cited by:

CitedPegler Ltd v Wang (UK) Ltd TCC 25-Feb-2000
Standard Conract – Wide Exclusions, Apply 1977 Act
The claimant had acquired a computer system from the defendant, which had failed. It was admitted that the contract had been broken, and the court set out to decide the issue of damages.
Held: Even though Wang had been ready to amend one or . .
CitedRuxley Electronics and Construction Ltd v Forsyth HL 29-Jun-1995
Damages on Construction not as Agreed
The appellant had contracted to build a swimming pool for the respondent, but, after agreeing to alter the specification to construct it to a certain depth, in fact built it to the original lesser depth, Damages had been awarded to the house owner . .
Lists of cited by and citing cases may be incomplete.

Damages, Construction

Updated: 01 May 2022; Ref: scu.238583

Skandia Property (Uk) Limited Vala Properties Bv v Thames Water Utilities Limited: 1997

The burden of proof in establishing betterment to reduce a damages award is on the defendant.

Citations:

(1997) 57 Con LR 65

Jurisdiction:

England and Wales

Cited by:

Appeal fromSkandia Property (UK) Limited Vala Properties Bv v Thames Water Utilities Limited CA 27-Jul-1999
The defendants were liable after a flood invaded and damaged the plaintiff’s premises. Having been advised professionally that the waterproofing system in the property would need replacing, the plaintiffs so replaced it but, it turned out, . .
CitedPegler Ltd v Wang (UK) Ltd TCC 25-Feb-2000
Standard Conract – Wide Exclusions, Apply 1977 Act
The claimant had acquired a computer system from the defendant, which had failed. It was admitted that the contract had been broken, and the court set out to decide the issue of damages.
Held: Even though Wang had been ready to amend one or . .
Lists of cited by and citing cases may be incomplete.

Construction, Damages

Updated: 01 May 2022; Ref: scu.238589

John Barker Construction Ltd v London Portman Hotel Ltd: 1996

An architect who had to decide whether to grant an extension of time under clause 25 of the JCT conditions would not have acted fairly and lawfully and his decision would be fundamentally flawed if he had not carried out a logical analysis in a methodical way of the impact of the relevant events on the contractor’s programme and made only ‘an impressionistic, rather than a calculated, assessment’ and: ‘I accept that the assessment of a fair and reasonable extension involves an exercise of judgment, but that judgment must be fairly and rationally based.’

Judges:

Mr Recorder Toulson QC

Citations:

(1996) 83 BLR 31

Cited by:

CitedCarillion Construction Ltd v Devonport Royal Dockyard Ltd CA 16-Nov-2005
The parties had disputed payments for subcontracting work on a major project. The matter had been referred to arbitration, and the claimants now appealed refusal of leave to appeal the adjudicator’s award.
Held: The dispute was complex and . .
Lists of cited by and citing cases may be incomplete.

Construction

Updated: 30 April 2022; Ref: scu.235382

Griffin v Midas Homes Ltd: 2000

In respect of part of their claim in an adjudication, the claimants failed to comply with the requirements of paragraph 1(3) of the statutory scheme for construction contracts which formed an implied term of the contract between the parties. That failure consisted of a lack of clarity in the notice of adjudication.
Held: As to that part of the claim, the adjudicator did not have jutisdiction. An adjudicator was held to have had authority to decide some of the questions put before him, but not others. Only the party that sought adjudication was liable for the adjudicator’s fees, expenses and costs in so far as they related to the matters which were outside the adjudicator’s jurisdiction.

Judges:

Judge Humphrey LLoyd QC

Citations:

(2000) 78 Con LR 152

Cited by:

CitedJohn Roberts Architects Ltd v Parkcare Homes (No. 2) Ltd TCC 25-Jul-2005
The defendant had taken a dispute to adjudication, but then abandoned those proceedings, upon which the adjudicator awarded costs against the defendant which the claimant now sought to enforce. The defendant argued that the award was outside the . .
Lists of cited by and citing cases may be incomplete.

Arbitration, Construction

Updated: 30 April 2022; Ref: scu.230380

Steamship Mutual Underwriting Association Ltd v Trollope and Colls Ltd: CA 1986

The employers sued the builders and architects alleging defects in the air conditioning system. Later, cracking and displacement of the walls was discovered, caused allegedly by not having sulphate resisting cement, and defects in the wall ties. Allegations were made against the contractors and the architects and also structural engineers. The question then arose whether the amendments raised new claims for the purposes of section 35 of the 1980 Act.
Held: May LJ said: ‘I think it is necessary to adopt a broad approach to these cases. At the stage of the issue of the writ or the service of the statement of claim, in the present context one is not, as I think, concerned with the minutiae of the cause of action which will ultimately have to be investigated at the trial. In the Limitation Act context, one asks in quite broad terms whether the relevant factual situation . . first came about, first was suable upon more than the three, six or twelve years previously. In the res judicata context one has to ask whether the issues in the hypothetical second action were realistically before the court in the hypothetical first action. Merely to rely upon the propositions which I have already quoted from Brunsden v Humphrey in the judgment of Bowen LJ, which was referred to in the judgment of Sankey LJ in Conquer v Boot , that it is a well settled rule of law that damages resulting from one and the same cause of action must be assessed and recovered once and for all, (entirely accurate though that is and I would not wish, with respect, to differ at all), nevertheless in the instant context I think that it effectively begs the whole question at the outset.’
and ‘In the present case, if one remembers what a cause of action is (for instance, to refer back to the dictum in Letang), if one looks to the size of this particular building, to its complexities, to other matters of degree, to the statement of claim before the proposed reamendment, to the attitude of the appellants’ solicitors in the correspondence at the material time, to which I have referred, and avoids what I think are unnecessary subtleties, I feel bound to agree with the learned judge where he concluded, having referred to the cases on what is a cause of action, the statement of claim in both its original and amended form related only to the air conditioning. I think that its effect was to narrow the causes of action so that they became confined to breaches of contract concerned with air conditioning and negligence resulting in damages to the air conditioning. In the light of the definitions of a cause of action already referred to, I do not think one can look only to the duty on a party, but one must look also to the nature and extent of the breach relied upon, as well as to the nature and extent of the damage complained of in deciding whether, as a matter of degree, a new cause of action is sought to be relied upon. The mere fact that one is considering what are, as it is said, after all only different defects to the same building, does not necessarily mean in any way that they are constituents of one and the same cause of action.
Thus I conclude that whether there is a new cause of action in any circumstances is a mixed question of law and fact. I am satisfied that the learned judge correctly directed himself on the law on this point, and not only am I unable to say that he applied the law incorrectly to the facts of the case, I think positively that he applied that law correctly to the facts of the case.’
and ‘In my opinion, to issue a writ against a party . . when it is not intended to serve a statement of claim, and where one has no reasonable evidence or grounds on which to serve a statement of claim against that particular party, is an abuse of the process of the court.’
Lloyd LJ said: ‘in each case it will depend on the facts whether the damage gives rise to a separate cause of action, or not’ and ‘there may be separate causes of action in relation to the same building, depending upon the facts of the case.’

Judges:

Lloyd LJ and May LJ

Citations:

[1986] 33 BLR 77

Statutes:

Limitation Act 1980 35

Jurisdiction:

England and Wales

Cited by:

CitedSavings and Investment Bank Ltd (in Liquidation) v Fincken CA 6-Nov-2001
When the court was asked to decide whether a proposed form of amendment to the pleadings would add an issue which was out of time, the court must look to the pleadings before and after the proposed amendment, and the factual issues which would have . .
CitedMcDonalds Corp and Another v Steel and Another CA 25-Mar-1994
The plaintiff company had sued the defendants in defamation with regard to a leaflet publishd and distributed by them. The defendants argued justification. The defendants appealed against an order striking out parts of their defence, saying that the . .
Lists of cited by and citing cases may be incomplete.

Construction, Limitation, Litigation Practice

Updated: 29 April 2022; Ref: scu.183221

Staveley Industries Plc (T/A Ei Whs) v Odebrecht Oil and Gas Services Ltd: TCC 8 Mar 2001

Contracts were entered into to design, engineer and supply equipment for installation on oil and gas rigs. The contractor sought to assert that these were contracts governed by the Act, and the provisions for dispute resolution applied. The court held that the act suggested that the construction was to take place on ‘the Land’ and that there was no intention to include offshore installations within the Act.

Citations:

Gazette 08-Mar-2001

Statutes:

Interpretation Act 1978, Housing Grants Construction and Regeneration Act 1996

Jurisdiction:

England and Wales

Contract, Construction, Arbitration

Updated: 28 April 2022; Ref: scu.89517

Pearce and High Ltd v Baxter and Another: CA 24 Mar 1999

The clause in JCT specifying procedures for claiming against contractors did not oust the employers’ common law rights. An employer failing to give notice under the defects liability clause in time, could still sue under common law for the defect.

Citations:

Times 24-Mar-1999, [1999] 66 Con LR 110

Jurisdiction:

England and Wales

Citing:

CitedWilliam Tompkinson and Sons Ltd v St Michaels Parochial Church Council 1990
. .

Cited by:

CitedPersimmon Homes (South Coast) Ltd v Hall Aggregates (South Coast) Ltd and Another TCC 10-Oct-2008
The parties had agreed for the sale of land under an option agreement. The builder purchasers now sought to exercise rights to adjust the price downwards.
Held: The provisions had been intended and had achieved a prompt and binding settlement . .
Lists of cited by and citing cases may be incomplete.

Construction

Updated: 28 April 2022; Ref: scu.84628

Andrews v Schooling: CA 1991

The plaintiff owned a 199 year lease of premises and sought compensation under the Act damp from the cellar. The defence said the development had not included work done on the cellar and therefore section 1 did not apply.
Held: The defence failed. If the owner of a plot of land instructs a builder to erect a dwelling house but he fails to include a damp course, leaving the house, not fit for human habitation. Parliament could not have intended that the builder would be free from any duty under section 1(1). The exception (and the exception to the exception) under subsection (2) would serve no purpose. Subsection (4) was conclusive in favour of the construction that includes nonfeasance within the scope of the duty. If a developer who is professionally qualified, e.g. an architect or surveyor, instructs a builder to erect a dwelling house or to convert an existing house into a number of separate dwellings. His instructions are detailed, but make no provision for inclusion of a damp course, which is necessary if the dwelling is to be fit for habitation when completed. The builder will be exempt under subsection (2). But the developer, who will not have physically done any work, is to be treated under subsection (4) as a person who has taken on the work. There was no difference between acts of commission and of omission.

Judges:

Balcombe LJ

Citations:

[1991] 1 WLR 783

Statutes:

Defective Premises Act 1972 1

Jurisdiction:

England and Wales

Cited by:

CitedAlderson, Alderson v Beetham Organisation Limited CA 2-Apr-2003
The claimants appealed rejection of their claim as out of time under the Act. The property was constructed in 1994, but came to suffer from damp. They were advised of the defect and possible action in 1995, but failed to begin proceedings until . .
Lists of cited by and citing cases may be incomplete.

Construction, Limitation

Updated: 27 April 2022; Ref: scu.180873

North Midland Building Ltd v Cyden Homes Ltd: CA 30 Jul 2018

The court considered the validity of a clause in a building contract which provided that, where there was a delay caused by an event for which the contractor was responsible, and that delay was concurrent with a delay for which the employer was responsible, such concurrent delay would not be taken into account when calculating any extension of time to the contract completion date. It was the appellant contractor’s case that this clause was contrary to what has come to be known as ‘the prevention principle’ and therefore ineffective.

Citations:

[2018[ EWCA Civ 1744

Links:

Bailii

Jurisdiction:

England and Wales

Construction, Contract

Updated: 25 April 2022; Ref: scu.620472

Revenue and Customs v Wetheralds Construction Ltd: UTTC 30 May 2018

VALUE ADDED TAX – reduced rate supply -energy saving materials – whether appellant’s Solid Roof System a supply of insulation for roofs within VATA 1994 Schedule 7A Group 2 – no – appeal allowed

Citations:

[2018] UKUT 173 (TCC)

Links:

Bailii

Jurisdiction:

England and Wales

VAT, Construction

Updated: 22 April 2022; Ref: scu.617296

Plant Construction Plc v Clive Adams Associates, JMH Construction Services (2): TCC 31 Mar 2000

The case had been remitted to the court to settle the apportionment of damages in a case of breach of contract, rather than in tort. When assessing levels of contribution causation alone is important but not the entire criteria. In cases where both parties would have had to act with due care and skill to avoid the damage, the question is whether a breach was causative, whether alone or as being one of concurrent causes with the other’s negligence, such that but for the concurrence of those causes the damage would not have occurred.

Judges:

Judge Hicks QC

Citations:

1996 ORB 750

Citing:

AppliedHeskell v Continental Express Ltd 1950
The court discussed how a warranty of authority could arise in an agent: ‘An agent who warrants that he has authority need warrant no more than the bare fact. In the absence of special circumstances, he makes no warranty or representation about how . .
Lists of cited by and citing cases may be incomplete.

Damages, Construction

Updated: 11 April 2022; Ref: scu.135952

McNicholas Plc v AEI Cables Limited: TCC 25 May 1999

The claimant had subcontracted to supply cabling on the defendant’s project. The contract provided both for the exclusive jurisdiction of the English courts but also for arbitration. The defendant applied for the action to be stayed and referred to arbitration. The claimant said the clause was ineffective being uncertain within s9 of the 1996 Act, and also unenforceable as an unfair contract term
Held: The reference clause was effective, and the court action should be stayed for arbitration. ‘Wherever possible, a court will seek to uphold a contract rather than to destroy it. In my judgment it is plain that clause 8 of this sub-contract has two purposes. First, it selected the law that was to be applied to the contract. The reference to the English Courts having exclusive jurisdiction over the agreement is curious since both parties are English companies and the works are in England so this stipulation may be redundant, but equally there may have been a good reason for it. It is however clear that clause 9 is intended to ensure that disputes in a wide variety of circumstances should either be referred to arbitration or should be subject to some other regime. I have no doubt that the reference to the English courts having jurisdiction can be read satisfactorily with clause 9 since it must be taken to be the parties’ intention that in so far as it was necessary to have recourse to any court to deal with any matter arising out of the agreement which could not be dealt with by the arbitrator then the English courts would be the appropriate court. ‘
The abrogation clause was strikingly unclear, but remained effective. The court approved the statement: ‘Incapable of being performed’ connotes something more than mere difficulty or inconvenience or delay in performing the arbitration. There must be some obstacle which must be overcome even if the parties are ready, able and willing to perform the agreement.’ The agreement did not provide the claimant of an opportunity to have its disagreement dealt with fairly if the defendant gave notice to abrogate the agreement to arbitrate, but no such notice had been given.
The clause was unreasonable under the 1977 Act because it risked one party being unable to have its complaint adjudicated upon, and also being unable to have adjudicated an unrelated matter.

Judges:

Humphrey Lloyd QC

Citations:

Unreported 25 May 1999

Statutes:

Arbitration Act 1996 9, Unfair Contract Terms Act 1977 13(1)

Jurisdiction:

England and Wales

Citing:

CitedLovelock Limited v Exportles CA 1968
The contract provided both that a dispute must to be referred to arbitration in London and also for any other dispute must be referred to arbitration in Moscow.
Held: The conflicting requirements for arbitration were so ambiguous as to be . .
CitedPaul Smith Ltd v H and S International Holdings Inc ChD 1991
The contract between the parties said both that any disupte should be referred to arbitration, and that ‘The Courts in England shall have exclusive jurisdiction over it to which jurisdiction the parties hereby submit.’ The plaintiffs said the . .
CitedRedland Aggregates Limited v Shephard Hill Civil Engineering Limited CA 11-Dec-1998
The opinion which the contract provided for the main contractor to hold under the 1984 edition of the FCEC form had to be bona fide, and perhaps also reasonable. . .
CitedBremer Vulkan Schiffbau und Maschineenfabrik v South India Shipping Coroporation HL 1981
The parties had referred their dispute to arbitration, but there had been inordinate delay, and the plaintiffs complained that the delay had prejudiced them, and sought an injunction to prevent further contuance of the arbitration, saying that the . .
CitedWest of England Ship Owners Mutual Insurance Association (Luxembourg) v Cristal Ltd (The Glacier Bay) CA 26-Oct-1995
An agreement giving to a ‘sole judge’ the power to make a final decision was effective, and there was no appeal from his decision. The defendant’s decision in his capacity as Convention administrator was as a final arbiter and was unreviewable.
Lists of cited by and citing cases may be incomplete.

Construction, Arbitration

Updated: 11 April 2022; Ref: scu.136037

Postermobile Plc v Kensington and Chelsea Royal London Borough Council: QBD 8 Jun 2000

A builder was convicted after having a hoarding erected which announced forthcoming building works, but where such works were not in fact begun within the three month rule. The conviction was upheld, since the regulations were quite clear. The rule was a relaxation, and it was for those taking advantage of that relaxation to bring themselves within it.

Citations:

Gazette 08-Jun-2000

Planning, Construction

Updated: 09 April 2022; Ref: scu.84817

Mark Wilkinson Furniture Ltd v Construction Industry Training Board: QBD 10 Oct 2000

The operation of installing kitchens could amount to work altering a building. Accordingly firms carrying out such installations were liable to pay a levy as a contribution to the industry’s training scheme. Although in many cases fittings might only be attached to buildings by screws, the fittings were intended to alter the character of a building, and counted as such.

Citations:

Times 10-Oct-2000

Statutes:

Industrial Training Levy (Construction Board) Order 1999 159

Citing:

See AlsoMark Wilkinson Furniture Limited and Construction Industry Training Board Admn 12-Jan-2000
. .

Cited by:

See alsoMark Wilkinson Furniture Limited and Construction Industry Training Board Admn 12-Jan-2000
. .
Lists of cited by and citing cases may be incomplete.

Land, Construction, Employment

Updated: 09 April 2022; Ref: scu.83411

Johnston v W H Brown Construction (Dundee) Ltd: IHCS 7 Jun 2000

The cost of employing an architect to draw up a schedule of defects under a building contract was not recoverable as damages. The rights under this contract required remediation of the defects discovered and listed, and did not envisage other expenses.

Citations:

Times 07-Jun-2000

Citing:

Appeal fromJohnston v W H Brown Construction (Dundee) Ltd OHCS 12-Nov-1999
An employer who had to prepare a schedule of defects in order to pursue a claim against his builder, and incurred both architects and legal costs in the preparation of the schedule was not able to claim such costs as consequential losses under the . .

Cited by:

CitedCetelem Sa v Roust Holdings Ltd CA 24-May-2005
The parties were engaged in arbitration proceedings. The claimant had sought and obtained an interim mandatory order intended to prevent the defendant dissipating its assets in anticipation of an adverse ruling. The defendant sought leave to appeal. . .
Lists of cited by and citing cases may be incomplete.

Damages, Construction

Updated: 09 April 2022; Ref: scu.82568

Johnston v W H Brown Construction (Dundee) Ltd: OHCS 12 Nov 1999

An employer who had to prepare a schedule of defects in order to pursue a claim against his builder, and incurred both architects and legal costs in the preparation of the schedule was not able to claim such costs as consequential losses under the contract. Such losses were not recoverable at common law.

Citations:

Times 12-Nov-1999

Statutes:

Scottish Building Contract with Contractor’s Design (Jan 1993 rev)

Cited by:

Appeal fromJohnston v W H Brown Construction (Dundee) Ltd IHCS 7-Jun-2000
The cost of employing an architect to draw up a schedule of defects under a building contract was not recoverable as damages. The rights under this contract required remediation of the defects discovered and listed, and did not envisage other . .
Lists of cited by and citing cases may be incomplete.

Construction

Updated: 09 April 2022; Ref: scu.82569

Jones v Tower Hamlets London Borough Council and Another: ChD 26 Oct 2000

The architect drew plans for buildings on a development completion of which was taken over by the council. The architect claimed breach of copyright in his plans. The expression of design ideas in an architectural drawing was capable of protection by copyright. An architect might see the plans drawn by another, absorb some of the ideas, and then re-express the ideas in his own way. He may not copy them. The line between them is a fine one. Was the new design a copy of the style or idea or of the expression of the style or idea. One is acceptable, the other is not. The degree of similarity, and method of preparation of the second article were important.

Citations:

Gazette 26-Oct-2000, Times 14-Nov-2000

Statutes:

Copyright Designs and Patents Act 1988

Intellectual Property, Construction

Updated: 09 April 2022; Ref: scu.82614

Customs and Excise Commissioners v Marchday Holdings Ltd: QBD 31 Jul 1995

A before and after test is to be used to see whether a work is a new building or a conversion of an old building.

Citations:

Ind Summary 31-Jul-1995

Jurisdiction:

England and Wales

Citing:

Appealed toCommissioners for Customs and Excise v Marchday Holdings Limited CA 11-Dec-1996
Extensive work on an existing building may be more than a conversion and therefore may be zero-rated. . .

Cited by:

Appeal fromCommissioners for Customs and Excise v Marchday Holdings Limited CA 11-Dec-1996
Extensive work on an existing building may be more than a conversion and therefore may be zero-rated. . .
Lists of cited by and citing cases may be incomplete.

VAT, Construction

Updated: 08 April 2022; Ref: scu.79734

British Telecommunications Plc v James Thomson and Sons (Engineers) Ltd: IHCS 28 Jan 1997

Main contractor’s insurance against a sub-contractor’s negligence relieved the sub-contractor of his duty of care.

Citations:

Times 28-Jan-1997

Jurisdiction:

England and Wales

Cited by:

Appeal fromBritish Telecommunications plc v James Thomson and Sons (Engineers) Ltd HL 29-Oct-1998
A sub-contractor would owe a duty of care to the main contractor and the insurer be entitled to stand subrogated to the main contractor where the sub-contractor was not nominated as being exempt from such duty in the insurance. . .
Lists of cited by and citing cases may be incomplete.

Construction

Updated: 08 April 2022; Ref: scu.78642

Energy Works (Hull) Ltd v MW High Tech Projects Uk Ltd and Others: TCC 24 Sep 2020

Hearing of preliminary issues to determine: i) the legal effect of an assignment by the First Defendant (‘MW’) to the Claimant (‘EWHL’) of MW’s sub-contract with the Part 20 Defendant (‘Outotec’); and ii) whether MW can pursue its claims for contribution against Outotec as direct claims, in respect of accrued rights under the sub-contract, or based on its liability for ‘the same damage’ pursuant to the Civil Liability (Contribution) Act 1978 (‘the 1978 Act’).

Judges:

Mrs Justice O’Farrell DBE

Citations:

[2020] EWHC 2537 (TCC)

Links:

Bailii

Statutes:

Civil Liability (Contribution) Act 1978

Jurisdiction:

England and Wales

Construction, Contract

Updated: 07 April 2022; Ref: scu.655941

Anstar (Harmonised Conditions for The Marketing of Construction Products : Judgment): ECJ 14 Dec 2017

Reference for a preliminary ruling – Harmonised conditions for the marketing of construction products – Harmonised standard EN 1090-1:2009+A1:2011 – Criteria for determining the scope of a standard adopted by the European Committee for Standardisation (CEN) in accordance with a mandate of the European Commission – Anchors to be fixed into concrete before it sets and used for fastening facade elements and masonry supports to the building frame

Citations:

C-630/16, [2017] EUECJ C-630/16

Links:

Bailii

Jurisdiction:

European

Construction

Updated: 02 April 2022; Ref: scu.602065

Cleveland Bridge Uk Ltd and Another v Multiplex Constructions (UK) Ltd: CA 31 Mar 2010

Citations:

[2010] EWCA Civ 449

Links:

Bailii

Jurisdiction:

England and Wales

Citing:

See AlsoCleveland Bridge UK Ltd v Multiplex Constructions (UK) Ltd TCC 31-Aug-2005
A third party television company sought access to the particulars of claim and other pleadings.
Held: HH Judge Wilcox said: ‘There can be no legitimate distinction drawn between decisions made in interlocutory proceedings and those at final . .
See AlsoMultiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd TCC 5-Jun-2006
. .
See AlsoMultiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd and Another CA 20-Dec-2006
. .
See AlsoMultiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd (No. 2) TCC 31-Jan-2007
. .
See AlsoMultiplex Construction (Uk) Ltd v Honeywell Control Systems Ltd TCC 8-Feb-2007
Application for permission to appeal. Jackson J considered whether permission to appeal should have been requested at the hearing: ‘It seems to me that I have got to interpret the provisions of Rule 52.3 and the provisions of the Practice Direction . .
See AlsoMultiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd (No. 2) TCC 6-Mar-2007
. .
See AlsoMultiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd (No 3) TCC 12-Mar-2007
. .
See AlsoCleveland Bridge UK Ltd and Another v Multiplex Constructions (UK) Ltd CA 27-Apr-2007
The court construed an agreement supplemental to a construction contract. . .
See AlsoMultiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd and Another CA 21-Dec-2007
. .
See AlsoMultiplex Construction Ltd v Cleveland Bridge Ltd and Another CA 6-Feb-2008
. .
See AlsoMultiplex Construction (Uk) Ltd v Cleveland Bridge UK Ltd and Another TCC 7-Feb-2008
. .
See AlsoMultiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd and Another TCC 19-Mar-2008
. .
See AlsoMultiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd and Another TCC 29-Sep-2008
. .
See AlsoMultiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd and Another (No 7) TCC 29-Sep-2008
Last stage of the Wembley stadium construction dispute. Jackson J, interpreting Carver said that it set out: ‘how the court ought to approach the matter in circumstances where: (a) one party has made an offer which was nearly but not quite . .
See AlsoCleveland Bridge UK Ltd and Another v Multiplex Constructions (UK) Ltd CA 19-Feb-2010
. .
Lists of cited by and citing cases may be incomplete.

Construction

Updated: 01 April 2022; Ref: scu.416096

Adam Architecture Ltd v Halsbury Homes Ltd: CA 2 Nov 2017

Appeal by a firm of architects in litigation concerning its entitlement to recover fees following termination of its engagement. The principal issue in this appeal is whether Section 111 of the 1996 Act applies only to interim payments or whether it also applies to payments due following completion of the works or termination of the contract.

Judges:

Jackson, Lindblom, Thirlwall LJJ

Citations:

[2017] EWCA Civ 1735

Links:

Bailii

Statutes:

Housing Grants, Construction and Regeneration Act 1996 111

Jurisdiction:

England and Wales

Construction, Contract

Updated: 01 April 2022; Ref: scu.598471

North Midland Building Ltd v Cyden Homes Ltd: TCC 2 Oct 2017

Part 8 claim brought by the claimant against the defendant in relation to what is said to be a point of contractual interpretation of one of the clauses of the contract agreed between the parties for the construction by the claimant of a sizeable house in the Midlands.

Judges:

Fraser J

Citations:

[2017] EWHC 2414 (TCC)

Links:

Bailii

Jurisdiction:

England and Wales

Construction

Updated: 30 March 2022; Ref: scu.595943