Judges:
Akenhead J
Citations:
[2012] EWHC 1972 (TCC), [2012] 6 Costs LO 862, 143 Con LR 79
Links:
Jurisdiction:
England and Wales
Construction, Costs
Updated: 03 November 2022; Ref: scu.463096
Akenhead J
[2012] EWHC 1972 (TCC), [2012] 6 Costs LO 862, 143 Con LR 79
England and Wales
Updated: 03 November 2022; Ref: scu.463096
Coulson J
[2012] EWHC 1956 (TCC)
England and Wales
Updated: 03 November 2022; Ref: scu.463090
Akenhead J
[2012] EWHC 1773 (TCC), [2012] BLR 503
England and Wales
Updated: 03 November 2022; Ref: scu.463095
The defendant neighbour had carried out construction works on a joint structure involving its demolition. He had not complied with the requirements of the 1917 Act.
Held: A neighbour doing work on a party wall without complying with the requirements of the Act was creating a nuisance, and he made himself liable for special damages, including some financial losses. A later award under the Act does not relieve a building owner from liability in nuisance or interference with rights of support for works undertaken before the date of the award, and he could not rely upon a defence in the Act, having later complied with it, to excuse his earlier wrong.
Evans LJ
Gazette 13-Dec-1996, Times 22-Nov-1996, [1997] 1 EGLR 136
London Building Acts (Amendment) Act 1939
England and Wales
Cited – Rodrigues v Sokal TCC 30-Jul-2008
The parties owned either half of a semi-detached residence. The defendant had undertaken substantial redevelopment works, and the claimant sought damages under the 1996 Act for his failures to follow that Act. The issues had been taken to . .
Lists of cited by and citing cases may be incomplete.
Updated: 03 November 2022; Ref: scu.83220
Edwards-Stuart J
[2012] EWHC 1509 (TCC), [2012] BLR 355
Updated: 03 November 2022; Ref: scu.461925
Brooke, Hale LJJ, David Steele J
[2002] EWCA Civ 9, [2002] Lloyd’s Law Rep PN 231, 83 Con LR 164, [2002] 17 EG 158
England and Wales
Updated: 01 November 2022; Ref: scu.188933
His Honour Judge Richard Seymour Q.C
[2003] EWHC 1487 (TCC)
England and Wales
Updated: 01 November 2022; Ref: scu.184341
The contractors appealed a decision that an arbitrator had jurisdiction to hear a claim against them in respect of works carried out on the Thelwall viaduct. The contractors denied that there had been a dispute which could found a reference, and no valid engineer’s decision within the time limit provided.
Held: The court must avoid an over-legalistic approach to interpretation of the contract. The engineer has a duty to act independently honestly and with fairness, but the rules of natural justice as such did not apply to his decision.
May, Rix, Hooper, LJJ
[2005] EWCA Civ 291, Times 22-Mar-2005, [2005] 1 WLR 2339, [2005] BLR 227, (2005) 21 Const LJ 640, 101 Con LR 26, [2005] 12 EG 219
England and Wales
Appeal from – Amec Civil Engineering Ltd v The Secretary of State for Transport TCC 11-Oct-2004
The court affirmed an interim arbitration award as to jurisdiction in an arbitration commenced by the Secretary of State against the contractors in relation to work carried out by them on the Thelwall viaduct. The court identified seven applicable . .
Cited – Tradax International v Cerrahogullari 1981
An express rejection of a claim is not required in every case to generate a dispute allowing a reference to arbitration. . .
Cited – Monmouthshire County Council v Costelloe CA 1965
A question arose under a contract including the ICE conditions as to whether there had historically been claims by the contractor which the Engineer had already determined under clause 66.
Held: There had been no such earlier dispute or . .
Cited – Ellerine Bros v Klinger CA 1982
The court was asked whether there was a dispute sufficient to allow a stay of court proceedings to allow an arbitration to proceed.
Held: If letters were written making some request or demand and the defendant did not reply, there was a . .
Cited – Collins (Contractors) Ltd v Baltic Quay Management (1994) Ltd CA 7-Dec-2004
The claimant sought payment under its invoice for construction works. The contractor gave notice of its intention to withhold payment, and then also sought to refer the matter to arbitration. The claimant said that the notice had prevented the . .
Cited – Halki Shipping Corporation v Sopex Oils Limited CA 19-Dec-1997
The court was aked whether there was a dispute sufficient to sustain a stay of court proceedings for arbitration under the Act.
Held: There was a dispute once money is claimed unless and until the defendants admit that the sum is due and . .
Cited – Panamena Europea Navigacion v Frederick Leyland and Co HL 1947
The parties had entered into an agreement providing for arbitration of any disputes. Lord Thankerton said: ‘By entering into the contract the respondents agreed that the appellant’s surveyor should discharge both these duties and therefore they . .
Cited – F and G Sykes (Wessex) v Fine Fare Ltd CA 1967
There was an agreement by which the plaintiffs agreed to breed and provide chicks to nominated growers, the number of chicks to be provided to be ‘not less than 30,000 per week nor more than 80,000 per week during the first year of the agreement and . .
Cited – Beaufort Developments (NI) Limited v Gilbert-Ash NI Limited and Others HL 26-Feb-1998
The contractual ability given to an arbitrator under standard JCT terms did not oust the court from assessing and prejudging the acts of the architect under a building contract. As to the means for interpreting documents, Lord Hoffmann said: ‘I . .
Cited – Canterbury Pipe Lines v The Christchurch Drainage Board 1979
(New Zealand Court of Appeal) ‘In Hatrick the term ‘fairness’ was avoided in the judgments, Richmond J saying that he resisted it partly because of its vagueness and partly because it might be regarded as equivalent to natural justice. . . . In our . .
Cited – Hounslow London Borough Council v Twickenham Gardens Development Limited 1971
The defendant, a building contractor, had been allowed into occupation of a site owned by the plaintiff council under a building contract. The council had sought to determine the contract by notice under its terms. The contractor refused to vacate . .
Appealed to – Amec Civil Engineering Ltd v The Secretary of State for Transport TCC 11-Oct-2004
The court affirmed an interim arbitration award as to jurisdiction in an arbitration commenced by the Secretary of State against the contractors in relation to work carried out by them on the Thelwall viaduct. The court identified seven applicable . .
Lists of cited by and citing cases may be incomplete.
Updated: 31 October 2022; Ref: scu.224061
[2005] EWCA Civ 432
England and Wales
Appeal from – Tombs v Wilson Connolly Ltd TCC 9-Nov-2004
. .
Lists of cited by and citing cases may be incomplete.
Updated: 31 October 2022; Ref: scu.224327
[2020] EWCA Civ 331
Housing Grants, Construction and Regeneration Act 1996
England and Wales
Updated: 31 October 2022; Ref: scu.648606
Waller, Keene, Dyson LJJ
[2007] EWCA Civ 663, [2007] BLR 430
England and Wales
Updated: 31 October 2022; Ref: scu.254545
[2006] EWCA Civ 1737, [2007] BLR 67, [2007] BusLR D1, 114 Con LR 81
Housing Grants, Construction and Regeneration Act 1996 108(1)
England and Wales
Updated: 31 October 2022; Ref: scu.247486
[2003] EWCA Civ 16
England and Wales
Updated: 31 October 2022; Ref: scu.181107
The defendants had carried out works of construction on the premises. They subcontracted the design, but not the supervision, of the works to architects. Years later there was a fire, which spread rapidly because of negligence in the design of a wall intended to restrain any fire. The architects said their duty was limited to responding to the first defendant’s requests for plans, and they did not themselves have responsibility for failures of specification.
Held: The omissions in design were the responsibility of the architects, who owed a duty of care to purchasers of a building as beneficial owners, where they had been involved in the construction, in respect of latent defects in the building of which there is no reasonable possibility of inspection.
Lord Justice Potter Lord Justice May Sir Anthony Evans
[2002] EWCA Civ 1823
England and Wales
Approved – Baxall Securities Ltd Norbain SDC Ltd v Sheard Walshaw Partnership TCC 30-Oct-2000
. .
Cited – Murphy v Brentwood District Council HL 26-Jul-1990
Anns v Merton Overruled
The claimant appellant was a house owner. He had bought the house from its builders. Those builders had employed civil engineers to design the foundations. That design was negligent. They had submitted the plans to the defendant Council for approval . .
Cited – Moresk Cleaners Ltd v Hicks 1966
If a dangerous defect arises as the result of a negligent omission on the part of an architect, he cannot excuse himself from liability on the grounds that he delegated the duty of design of the relevant part of the building works, unless he obtains . .
Cited – Henderson v Merrett Syndicates Ltd HL 25-Jul-1994
Lloyds Agents Owe Care Duty to Member; no Contract
Managing agents conducted the financial affairs of the Lloyds Names belonging to the syndicates under their charge. It was alleged that they managed these affairs with a lack of due careleading to enormous losses.
Held: The assumption of . .
See Also – Bellefield Computer Services Limited, Unigate Properties Limited; Unigate Dairies Limited; Unigate (Uk) Limited; Unigate Dairies (Western) Limited v E Turner and Sons Limited Admn 28-Jan-2000
The Defendant builders constructed a steel building to be used as, inter alia. a dairy. The original owners sold it to the appellants. A fire spread from the storage area to the rest of the dairy and caused much damage. The Builders, had they . .
Cited – Sahib Foods Limited and Co-operative Insurance Society Limited v Paskin Kyriakides Sands (A Firm) TCC 3-Mar-2003
The claimants were lessees of premises, and the second claimants had contracted to purchase it. The premises burned down, and the claimants sought damages from the architect respondents. The fire began because of negligence by the claimant’s . .
Cited – Independiente Ltd and others v Music Trading On-Line (HK) Ltd and others ChD 13-Mar-2003
The claimants claimed damages for the sale by the defendants in the UK of CD’s manufactured for sale only in the far East. The defendants challenged the right of a claimant phonographic society to have the right to sue on behalf of its members.
Lists of cited by and citing cases may be incomplete.
Updated: 27 October 2022; Ref: scu.178522
[1998] EWHC QB 335
England and Wales
Updated: 27 October 2022; Ref: scu.163127
The court provided an interpretation of the requirement on a contractor to attend ‘regularly’ and ‘diligently’ at a construction project.
Ind Summary 19-Dec-1994, Times 16-Nov-1994
England and Wales
Updated: 27 October 2022; Ref: scu.90390
A main employer may apply to the court for the construction of the meaning of sub-contracts with main contractor. A declaration was available to a Plaintiff in respect of sub-contractors only if part of scheme.
Times 23-Jan-1996, Ind Summary 12-Feb-1996
England and Wales
Updated: 27 October 2022; Ref: scu.84345
Beldam LJ said: ‘It seems to me implicit that the demand made by the sub-contractor should state the amount of the damages sustained by the default. But it does not follow that, because the main contractor must state the amount of the damages, the surety is entitled to question the amounts claimed by arguing that they are excessive or have not been incurred. It goes without saying that such a statement of damage must be made in good faith.’
Beldam LJ
(1994) 66 BLR 42
England and Wales
Appeal from – Trafalgar House Construction (Regions) Ltd v General Surety and Guarantee Co Ltd HL 4-Jul-1995
The main contractors for the construction of a new leisure complex for a borough council entered into a subcontract for the groundworks. The subcontractor and the appellants provided a Bond for 10 percent of the value of the subcontract on condition . .
Lists of cited by and citing cases may be incomplete.
Updated: 27 October 2022; Ref: scu.538239
A builder was sued for damages, and sought to set off against the damages claimed an as yet unquantified cross claim which was dependent upon a valuation to be carried out, that claim was insufficiently certain or ascertained to permit it to be used by way of set off.
Ind Summary 15-Feb-1993
England and Wales
Updated: 26 October 2022; Ref: scu.78040
Claim by purchasers of new houses about faults in them.
[2019] EWHC 1134 (TCC)
England and Wales
Updated: 24 October 2022; Ref: scu.640372
VAT – dwelling construction – business intention in obtaining planning permission not displaced by time of claim – whether entitled to refund under DIY Housebuilder scheme — no
[2018] UKFTT 542 (TC)
England and Wales
Updated: 24 October 2022; Ref: scu.632287
Lord Justice Kay Lord Justice Aldous Lord Justice Rix
[2003] EWCA Civ 170, [2003] BLR 271
England and Wales
Updated: 23 October 2022; Ref: scu.179581
The claimant appealed an order after a trial in a construction dispute.
Held: The judge had not properly understood the figures before him in a difficult case. The judgment was adjusted accordingly
[2004] EWCA Civ 691
England and Wales
See also – Medtia v Hamid and Another (Costs) CA 21-May-2004
Appeal against stay – costs . .
See also – Medtia v Hamid and Another (Costs) CA 21-May-2004
Appeal against stay – costs . .
Lists of cited by and citing cases may be incomplete.
Updated: 23 October 2022; Ref: scu.197977
[2020] EWCA Civ 114
England and Wales
Updated: 23 October 2022; Ref: scu.647014
[2006] EWHC 1771 (TCC)
England and Wales
Updated: 22 October 2022; Ref: scu.244134
The claimants appealed rejection of their claim as out of time under the Act. The property was constructed in 1994, but came to suffer from damp. They were advised of the defect and possible action in 1995, but failed to begin proceedings until 2001. The claimant said the limitation period began when remedial works failed.
Held: Section 1 imposes a duty of care upon builders of dwellings. 1(5) sets a limitation period of 6 years, but contains a proviso where work is done after completion ‘to rectify the work . . already done’. Parliament intended that there should be a fresh cause of action for breach of the duty to provide a dwelling fit for habitation when the further work did not rectify the original work as intended. The appeal was allowed.
Lord Justice Aldous Lord Justice Judge Lord Justice Longmore
[2003] EWCA Civ 408, Times 19-Apr-2003, Gazette 12-Jun-2003, [2003] 1 WLR 1686
Defective Premises Act 1972 1(5)
England and Wales
Cited – Andrews v Schooling CA 1991
The plaintiff owned a 199 year lease of premises and sought compensation under the Act damp from the cellar. The defence said the development had not included work done on the cellar and therefore section 1 did not apply.
Held: The defence . .
Lists of cited by and citing cases may be incomplete.
Updated: 22 October 2022; Ref: scu.180458
[2010] ScotCS CSOH – 125, 2011 Rep LR 18, 2010 GWD 32-667
Scotland
Updated: 21 October 2022; Ref: scu.425214
Lord Justice Mummery Lord Justice Rix Lord Justice Ward
[2004] EWCA Civ 119
England and Wales
See Also – Daly and Another v Sheikh CA 7-May-2002
Application for leave to appeal . .
See Also – Daly and Another v Sheikh CA 24-Oct-2002
Application for leave to appeal . .
See Also – Daly and Another v Sheikh CA 24-Oct-2002
Application for leave to appeal . .
See Also – Daly and Another v Sheikh CA 7-May-2002
Application for leave to appeal . .
Lists of cited by and citing cases may be incomplete.
Updated: 21 October 2022; Ref: scu.193485
VALUE ADDED TAX – DIY Builders scheme for refund of VAT – whether construction met condition in Note 2(d) to Group 5 Schedule 8 VATA – Lady Pearson applied – appeal allowed – whether building an annexe also considered – whether prohibition of separate use or disposal also considered – observations on aptness of penalties letter issued with initial rejection (without proper reasons) of claim – costs considered.
[2019] UKFTT 277 (TC)
England and Wales
Updated: 21 October 2022; Ref: scu.637837
Mrs Justice Farbey
[2020] EWHC 87 (QB)
England and Wales
Updated: 20 October 2022; Ref: scu.647446
His Honour Judge Raynor QC
[2014] CILL 3506, 153 Con LR 179,, [2014] EWHC 280 (TCC)
England and Wales
Updated: 19 October 2022; Ref: scu.521248
FTTTx Construction Industry Scheme – Appeal against cancellation of registration for gross payment – ‘Compliance test’ – Whether there was a reasonable excuse – No – Appeal dismissed – section 66 and schedule 11 Finance Act 2004 – Regulation 32 Income Tax (Construction Industry Scheme) Regulations 2005
[2010] UKFTT 269 (TC)
Finance Act 2004 66 Sch 11, Income Tax (Construction Industry Scheme) Regulations 2005 32
England and Wales
Updated: 19 October 2022; Ref: scu.422282
What makes a claim a ‘new claim’ as defined in section 35(2) of the Limitation Act 1980 is not the newness of the case according to the type or quantum of the remedy claimed, but the newness of the cause of action that it involves. A cause of action is a set of facts that enable one person to obtain a remedy from another; as opposed to a form of action used as a convenient and succinct description of a particular category of factual situation.
Auld, Hale and Dyson LJJ
[2003] EWCA Civ 1882
England and Wales
Cited – Rhone-Poulenc Rorer International Holdings Inc and Another v Yeda Research and Development Co Ltd ChD 16-Feb-2006
The patent application had been presented to the European Patent Office and granted only after 13 years. The claimant now appealed refusal to allow amendment of its claim to allow a claim in its sole name. The defendant argued that it was out of . .
Cited – Dowson and Others v Northumbria Police QBD 30-Apr-2009
Nine police officers claimed damages for alleged harassment under the 1997 Act by a senior officer in having bullied them and ordered them to carry out unlawful procedures. Amendments were sought which were alleged to be out of time and to have . .
Lists of cited by and citing cases may be incomplete.
Updated: 19 October 2022; Ref: scu.191208
Application to enforce arbitration award.
Fraser J
[2016] EWHC 1946 (TCC)
England and Wales
Updated: 13 October 2022; Ref: scu.567836
[1998] EWHC Technology 285
England and Wales
Updated: 12 October 2022; Ref: scu.201762
[2001] EWCA Civ 2088
England and Wales
Updated: 11 October 2022; Ref: scu.218624
A developer sought to set off input taxes paid in the redevelopment of a former residential boarding school as a family home.
Held: The taxpayer’s appeal succeeded.
[2004] UKVAT V18489
England and Wales
Appeal from – Commissioners of Customs and Excise v Jacobs ChD 22-Oct-2004
. .
At VAT Tribunal – Revenue and Customs v Jacobs CA 22-Jul-2005
The taxpayer had converted a former residentional boarding school into a substantial private residence. He had sought to claim over andpound;300,000 VAT inputs. The Commissioners appealed the finding that he was so entitled.
Held: ‘works . .
Lists of cited by and citing cases may be incomplete.
Updated: 11 October 2022; Ref: scu.195300
A project manager had a duty to ensure that all relevant and normal insurances were in place as the building project got under way, including professional negligence insurance of architects and designers.
Times 03-Dec-1998
England and Wales
Updated: 11 October 2022; Ref: scu.84834
A building contract contained the following clause:-‘ Twelfth, The Company reserve power during the progress of the work to make any alterations, additions, or deductions, or to vary from or alter the plans or materials as they may consider advisable, without in any respect vitiating this contract. This shall only be done under a written order from the Company’s engineer, and allowance will be made for such alterations at the rates in the schedule. The contractors shall not at their own hand, or without a written order from the Company’s engineer, be entitled to make any such alterations or additions, and no allegation by the contractors of knowledge of acquiescence in such alterations or additions on the part of the Company, their engineers or inspectors, shall be accepted or available as equivalent to the certificate of the engineer, or as in any way superseding the necessity of such certificate as the sole warrant for such alterations or additions.’ In a claim for payment on account of greater weight of metal in certain iron girders than was specified in the contract, where it was contended that there had been verbal consent and acquiescence on the part of the employers, and that the extra weight had been certified under the certificates of the defenders’ engineer- held [ rev. judgment of majority of Court of Session] that the terms of the contract excluded any such claim as was made, looking to the circumstances of the case, and to the fact that the forms of certificate by the engineer did not in any way bear out the view that there had been a ratification.
Lord Chancellor, Lord Hatherley, Lord Blackburn, and Lord Gordon
[1878] UKHL 777, 15 SLR 777
Scotland
Updated: 11 October 2022; Ref: scu.646308
[2002] EWCA Civ 320
England and Wales
Updated: 06 October 2022; Ref: scu.216989
Ramsay J
[2012] EWHC 396 (TCC), 141 ConLR 151
England and Wales
Updated: 06 October 2022; Ref: scu.452416
The court heard applications in adjudication enforcement proceedings between consultants and their employer, issues being raised about the extent to which the construction contract between the parties was in writing for the purposes of Section 107 of the Housing Grants, Construction and Regeneration Act 1996 (‘HGCRA’) and in relation to the extent and scope of the incorporation of the Scheme for Construction Contracts in circumstances in which the underlying contract does not comply with Section 108 of the HGCRA. This latter issue encompasses another issue which is whether the adjudicator was appointed by the correct nominating body
Akenhead J
[2011] EWHC 3191 (TCC), [2012] 9 EG 152, [2012] CILL 3124,, 140 Con LR 111, [2012] BLR 83
Updated: 05 October 2022; Ref: scu.451492
Akenhead J
[2011] EWHC 3464 (TCC), (2011) 142 ConLR 178
Updated: 05 October 2022; Ref: scu.451490
Application for injunction against subcontractor on substantial building project.
Akenhead J
[2011] EWHC 3157 (TCC)
Updated: 05 October 2022; Ref: scu.451482
Akenhead J
[2013] EWHC 3025 (TCC), [2014] 1 Costs LO 39
England and Wales
Updated: 05 October 2022; Ref: scu.516612
Her Honour Judge Frances Kirkham
[2003] EWHC 958 (TCC), (2004) 20 Const LJ 24
England and Wales
Updated: 04 October 2022; Ref: scu.181637
HH Judge Eyre QC
[2019] EWHC 3488 (TCC)
England and Wales
Updated: 04 October 2022; Ref: scu.646071
VAT – Do-It-Yourself Builders and Converters Scheme – VATA 1994 s35and Sch 8 Group 5 Note (2)(c) – whether prohibition on separate use or disposal of property – appeal allowed
[2011] UKFTT 835 (TC)
England and Wales
Updated: 04 October 2022; Ref: scu.450954
Construction Industry Scheme – removal of gross payments status – reasonable excuse – proportionality.
[2009] UKFTT 292 (TC)
England and Wales
Updated: 04 October 2022; Ref: scu.409128
Construction Industry Scheme – Appeal against cancellation of registration for gross payment – ‘Compliance test’ – Whether there was a reasonable excuse – Yes – Appeal Allowed – section 66 and schedule 11 Finance Act 2004 – Regulation 32 Income Tax (Construction Industry Scheme) Regulations 2005
[2009] UKFTT 380 (TC)
Income Tax (Construction Industry Scheme) Regulations 2005
England and Wales
Updated: 04 October 2022; Ref: scu.409139
VALUE ADDED TAX – ZERO RATING – Construction of buildings for a relevant residential purpose – whether an extension to an existing building – yes – whether additional dwellings created – no – Appeal dismissed – note 16(b) item 2 group 5 schedule 8 VATA 1994
[2009] UKFTT 296 (TC)
England and Wales
Updated: 04 October 2022; Ref: scu.409122
Sub-contractors in the construction industry; Construction Industry Scheme; removal of Gross Payments Status; appeal under section 67 Finance Act 2004; ‘compliance test’; ‘reasonable excuse’ for failure of the compliance test; ‘exceptional’ business conditions.
[2009] UKFTT 302 (TC)
England and Wales
Updated: 04 October 2022; Ref: scu.409118
[2006] EWCA Civ 936
England and Wales
Updated: 04 October 2022; Ref: scu.242971
[2019] EWHC 2846 (TCC)
England and Wales
See Also – Kivells Ltd v Torridge District Council (Costs) TCC 31-Oct-2019
. .
Lists of cited by and citing cases may be incomplete.
Updated: 04 October 2022; Ref: scu.645920
Akenhead J
[2012] EWHC 1996 (TCC), 144 Con LR 211
England and Wales
Updated: 04 October 2022; Ref: scu.463093
Stanley Burnton, Aikens, Elias LJJ
[2012] EWCA Civ 64
England and Wales
Updated: 04 October 2022; Ref: scu.450548
FTTTx Cancellation of Gross Payment Status under s66(1) Finance Act 2004; reasonable excuse for failures; trading problems; use of discounted invoice system; proportionality.
[2009] UKFTT 286 (TC)
England and Wales
Updated: 01 October 2022; Ref: scu.408989
There was no debt arising under a building contract which could be the subject of a garnishee order where there was no ’cause of action’ and no debt until an architect’s certificate had been issued.
Lord Goddard CJ said: ‘. . until the architect has given a certificate, the builder has no right to receive any sum of money from his employer by what I may call a drawing on account. He must get a certificate from the architect . . until the contractor can produce to the building owner a certificate he cannot receive anything.’
Lord Goddard, CJ, Havers, J
[1957] 1 WLR 1102
England and Wales
Cited – Taurus Petroleum Limited v State Oil Marketing Company of The Ministry of Oil, Republic of Iraq SC 25-Oct-2017
The parties disputed their contract arrangements. It was referred to an arbitration in London, but applying Iraqi law. The respondent failed to meet the award made against it, and the claimant sought to enforce the award here by means of third party . .
Lists of cited by and citing cases may be incomplete.
Updated: 01 October 2022; Ref: scu.646123
Mrs Justice O’Farrell DBE
[2019] EWHC 3585 (TCC)
Utilities Contracts Regulations 2016
England and Wales
Updated: 01 October 2022; Ref: scu.646070
VAT – DIY builders and converters refund scheme – whether building ceased to be existing building – whether what was retained was no more than a single facade – whether its retention a condition or requirement of statutory planning consent or similar permission – note (18), Group 5, Sch 8 VATA
[2011] UKFTT 652 (TC)
England and Wales
Updated: 29 September 2022; Ref: scu.449428
Claim for unpaid fees which the Claimants allege are due in respect of design work carried out by the Claimants for the redevelopment of the Marshall Street Baths and an adjacent car park in Poland Street, in Westminster
[2019] EWHC 3225 (TCC)
England and Wales
Updated: 29 September 2022; Ref: scu.645929
[2019] EWHC 3060 (TCC)
England and Wales
Updated: 29 September 2022; Ref: scu.645925
His Honour Judge Stephen Davies
[2019] EWHC 140 (TCC)
England and Wales
Updated: 29 September 2022; Ref: scu.634352
Laddie J
[2005] EWHC 1294 (Ch)
England and Wales
Cited – Shaw (Inspector of Taxes) v Vicky Construction Ltd ChD 6-Dec-2002
The General Commissioner had held that an inspector’s refusal to renew a certificate allowing the taxpayer construction company to pay its sub-contractors without deducting income tax, infringed that company’s rights. The inspector appealed.
Lists of cited by and citing cases may be incomplete.
Updated: 27 September 2022; Ref: scu.227944
Ramsey J
[2007] EWHC 855 (TCC)
England and Wales
Updated: 25 September 2022; Ref: scu.252355
[2005] EWHC 1558 (Ch)
Taxes Management Act 1970 56(6), General Commissioners (Jurisdiction and Procedure) Rules 1994 20, Income and Corporation Taxes Act 1988 561(9)
England and Wales
Updated: 25 September 2022; Ref: scu.228595
industrial training levy
[2004] EWHC 537 (Admin)
England and Wales
Updated: 25 September 2022; Ref: scu.195548
Mrs Justice Steyn
[2019] EWHC 3162 (Admin)
Building (Amendment) Regulations 2018
England and Wales
Updated: 25 September 2022; Ref: scu.645808
Mrs Justice O’Farrell DEB
[2019] EWHC 2547 (TCC)
Housing Grants, Construction and Regeneration Act 1996
England and Wales
Updated: 22 September 2022; Ref: scu.645919
Edwards-Stuart J
[2011] EWHC 2378 (TCC)
Updated: 20 September 2022; Ref: scu.444603
Lord Justice Peter Gibson Lord Justice Keene Lord Justice Clarke
[2004] EWCA Civ 1733, 98 Con LR 1
England and Wales
Updated: 19 September 2022; Ref: scu.220507
Malaysia
[1987] UKPC 4
Commonwealth
Updated: 17 September 2022; Ref: scu.443451
Construction Industry Scheme – Cancellation of registration for gross payment (Finance Act 2004 s.66) – Whether there was a ‘reasonable excuse’ (Finance Act 2004 Sch 11 para 4(4)(a)) – Proportionality – Appeal dismissed
[2011] UKFTT 290 (TC)
England and Wales
Updated: 17 September 2022; Ref: scu.443050
Appeal against penalties imposed for the late submission of ten monthly CIS returns on the grounds that not all the returns were received from HMRC – those received were posted on time but delayed by the postal service- the Appellant had reported the nil returns by telephone.
Radford
[2011] UKFTT 76 (TC)
Updated: 17 September 2022; Ref: scu.442813
Lord Justice Carnwath Lord Justice Sedley Lord Justice Dyson
[2006] EWCA Civ 875
England and Wales
Updated: 16 September 2022; Ref: scu.242878
[2000] EWCA Civ 378
England and Wales
Updated: 16 September 2022; Ref: scu.218689
[2002] EWCA Civ 805
England and Wales
Updated: 16 September 2022; Ref: scu.217213
[2002] EWHC 220 (Technology)
England and Wales
See Also – Daraydan Holdings Limited, Cairn Estates Limited and Others v Solland International Limited and Others ChD 26-Mar-2004
The court was asked whether Lister and Co v Stubbs 45 ChD 1, a decision of the Court of Appeal, was binding on him or whether he could apply the Privy Council’s decision in Attorney General for Hong Kong v Reid
Held: On the facts of the case . .
Lists of cited by and citing cases may be incomplete.
Updated: 15 September 2022; Ref: scu.170072
[2006] EWCA Civ 1522
England and Wales
Updated: 14 September 2022; Ref: scu.245997
[2004] EWHC 393 (TCC)
England and Wales
See Also – AMEC Capital Projects Ltd v Whitefriars City Estate Ltd TCC 19-Sep-2003
Application to enforce adjudicators award, and application to stay same. . .
Appeal from – AMEC Capital Projects Ltd v Whitefriars City Estates Ltd CA 28-Oct-2004
Alleged bias and procedural unfairness by an adjudicator appointed to determine a dispute in relation to a construction contract.
Held: The principles of the common law rules of natural justice and procedural fairness were two-fold. A . .
Lists of cited by and citing cases may be incomplete.
Updated: 14 September 2022; Ref: scu.219228
The land owner had elected to pay VAT on the purchase of land. It sought to recover that VAT. The Commissioners appealed an order allowing that.
Held: Ther were three transactions, the purchase, the sale, and a development contract. The input tax paid in carrying out the building contract were recoverable. Was the land therefore used ‘for the purpose of the taxpayer’s taxable transaction’, namely the development contract? The cost of the land was not a component of the costs in the same way that the materials were. The mere commercial link was insufficient. The transactions had to be looked at separately in VAT law, component by component.
Lord Justice Mantell Lord Phillips Of Worth Matravers, Mr Lord Justice Jacob
[2003] EWCA Civ 1662, Times 21-Nov-2003
England and Wales
Cited – BLP Group v Commissioners of Customs and Excise ECJ 6-Apr-1995
The use of taxable goods for an exempt transaction disallowed a claim against VAT input tax. The use in that provision of the words ‘for transactions’ shows that to give the right to deduct under paragraph 2, the goods or services in question must . .
Cited – Midland Bank plc v Customs and Excise Commissioners ECJ 8-Jun-2000
If there is a clear and direct link between the purchase of goods and their use in output transactions on which VAT was payable, input tax was deductible even if VAT was not deductible in respect of all the supplies. Where the link is indirect than . .
Cited – Abbey National Plc v Commissioners of Customs and Excise ECJ 22-Feb-2001
Where a part or whole of a business was sold as a going concern, not all the VAT on the expenses of the sale was to be set off against VAT. The entire amount of VAT could only be set off where the assets sold were sold as a properly identifiable . .
Cited – Card Protection Plan Ltd v Commissioners of Customs and Excise ECJ 25-Feb-1999
A company procuring insurance purchases for credit card protection was as exempt from VAT as was the insurer. A provision which restricted the ability to claim such exemption to those registered as insurers under national was invalid under European . .
Lists of cited by and citing cases may be incomplete.
Updated: 14 September 2022; Ref: scu.188107
In acting under clause 66 of the ICE conditions, the Engineer was in the intermediate position of a quasi-arbitrator. The House described in terms of ‘fairness’ the duty of an architect when acting not as an arbitrator or quasi-arbitrator but in the role of valuer or certifier.
An action for damages for negligence will lie against a valuer to whom the parties have referred the question of valuation if one of them suffers loss as the result of his negligent valuation.
Lord Reid spoke of a duty to act in a fair and unbiased manner or fairly and impartially. Viscount Dilhorne regarded an honest exercise of professional skill and judgment as enough.
Lord Reid, Lord Hodson, Lord Morris and Lord Salmon, Viscount Dilhorne
[1974] AC 727, [1974] 1 All ER 859, [1974] 2 WLR 295, [1974] 1 Lloyds Rep 318
England and Wales
Cited – Canterbury Pipe Lines v The Christchurch Drainage Board 1979
(New Zealand Court of Appeal) ‘In Hatrick the term ‘fairness’ was avoided in the judgments, Richmond J saying that he resisted it partly because of its vagueness and partly because it might be regarded as equivalent to natural justice. . . . In our . .
Lists of cited by and citing cases may be incomplete.
Updated: 12 September 2022; Ref: scu.224303
[2002] EWCA Civ 1382
England and Wales
See Also – Ferson Contractors Limited v Levolux A T Limited CA 22-Jan-2003
. .
Lists of cited by and citing cases may be incomplete.
Updated: 11 September 2022; Ref: scu.217530
Court Service Enforcement of an adjudicator’s decision; adjudication not subject to Housing Grants, Regeneration and Construction Act 1996; jurisdiction where terms of contract in dispute; applicability of Shepherd v Mecright; applicability of Unfair Terms in Consumer Contracts Regulations 1999.
Held: The contract was governed by an adjudication clause, the adjudicator had jurisdiction to determine whether the contract varying the construction contract was enforceable or lacked consideration, the adjudication clause was not unfair and was binding on Mr Beckingham, the adjudicator’s decision would be enforced and there would be judgment for Westminster in the sum claimed. This judgment was made in writing and was handed down by the court. For the purposes of paragraph 5.12 of 52PD-19 (Practice Direction – Appeals), this written judgment is to be taken as replacing an official recording and approved transcript of the judgment.
His Honour Judge Thornton QC
[2004] EWHC 138 (TCC), 94 Con LR 107, [2004] BLR 163, [2004] BLR 265, [2004] TCLR 8
England and Wales
Updated: 11 September 2022; Ref: scu.201843
Lord Justice Brooke Lord Justice Mance Mr Justice Parke
[2004] EWCA Civ 115, [2004] BLR 153, [2015] 1 WLR 785, 100 Con LR 1
England and Wales
Updated: 11 September 2022; Ref: scu.193912
The claimant said that the respondent had awarded a contract for works at the House of Commons disregarding its obligations under European law as regards open tendering.
[1999] EWHC Technology 199, 1996 ORB No 1151, (1999) 67 Con LR 1
Public Works Contracts Regulations 1991
England and Wales
Cited – Rewe-Zentralfinanz eG v Landwirtschaftskammer fur das Saarland (Judgment) ECJ 16-Dec-1976
‘the right of individuals to rely on the directly effective provisions of the Treaty before national courts is only a minimum guarantee and is not sufficient in itself to ensure the full and complete implementation of the Treaty’
1. The . .
Cited – Commission v Denmark ECJ 22-Jun-1993
Opinion – Tesauro AG said: ‘where a public contract falls to be awarded, it is precisely because the procedure is a competition that it must be ensured that all those who take part have an equal chance; otherwise, it would no longer be a public . .
Cited – Prebble v Television New Zealand Ltd PC 27-Jun-1994
(New Zealand) The plaintiff, an MP, pursued a defamation case. The defendant wished to argue for the truth of what was said, and sought to base his argument on things said in Parliament. The plaintiff responded that this would be a breach of . .
See Also – Harmon CFEM Facades (UK) Ltd v The Corporate Officer of the House of Commons TCC 29-Jun-2000
The company began a claim for damages for the failure to complete an award of a contract, but then went into voluntary liquidation. The defendant refused payment claiming that it would be used only for payment of the insolvency practitioner’s costs. . .
Cited – Montpellier Estates Ltd v Leeds City Council QBD 24-Jun-2010
The defendant sought to strike out certain parts of the claim against it relating to the tendering process for works on a substantial development. It was said that the defendant had given improper preference for the development of its own site.
Lists of cited by and citing cases may be incomplete.
Updated: 11 September 2022; Ref: scu.135813
Ramsey J
[2013] EWHC 1693 (TCC), [2014] 1 WLR 1
England and Wales
Updated: 10 September 2022; Ref: scu.510900
The claimants were main contractors on a construction project. The respondents were sub-contractors. After difficulties, the sub-contractor was ejected from the site. The issue was as to the jurisdiction of the adjudicator. Was the project, to create a sewage station, a ‘construction operation’ within the Act?
Held: The sum was due under the contract irrespective of whether an adjudicator also found it to be due. The contract could not be re-read to exclude the arbitration requirement. In this case the contractors were unlikely to succeed in any attempt to deny the sub-contractors their right to payment for works done, and payment should not be delayed for a set off claim. The judge was entitled, in her discretion, to make an interim award.
The Hon Mr Justice Latham
[2002] EWCA Civ 459, (2002) 93 Con LR 26
Housing Grants, Construction and Regeneration Act 1996
England and Wales
Cited – Swain v Hillman CA 21-Oct-1999
Strike out – Realistic Not Fanciful Chance Needed
The proper test for whether an action should be struck out under the new Rules was whether it had a realistic as opposed to a fanciful prospect of success. There was no justification for further attempts to explain the meaning of what are clear . .
Lists of cited by and citing cases may be incomplete.
Updated: 09 September 2022; Ref: scu.171203
[2002] EWCA Civ 310, 83 Con LR 132
England and Wales
Updated: 09 September 2022; Ref: scu.168085
The claimant (aged 6) sought damages after being hurt when other children playing on a building site threw stones from the site, hitting him as he passed by.
Held: The case raised questions of law and it was incumbent on the judge to provide detailed findings on the facts. A question of law was arguable, but the court was unable to determine the issue without the necessary findings of fact. The case would be remitted for retrial before a different judge.
[2004] EWCA Civ 345, Times 12-Apr-2004
England and Wales
Cited – Overseas Tankship (UK) Ltd v Miller Steamship Co Pty (The Wagon Mound) (No 2) PC 25-May-1966
(New South Wales) When considering the need to take steps to avoid injury, the court looked to the nature of defendant’s activity. There was no social value or cost saving in this defendant’s activity. ‘In the present case there was no justification . .
Cited – Jolley v Sutton London Borough Council HL 24-May-2000
An abandoned boat had been left on its land and not removed by the council. Children tried to repair it, jacked it up, and a child was injured when it fell. It was argued for the boy, who now appealed dismissal of his claim by the Court of Appeal, . .
Cited – Smith v Littlewoods Organisation Limited (Chief Constable, Fife Constabulary, third party); Maloco v Littlewoods Organisation Ltd HL 1987
The defendant acquired a semi derelict cinema with a view to later development of the site. A fire started by others spread to the pursuer’s adjoining property.
Held: The defendants were not liable in negligence. The intervention of a third . .
Cited – Goldman v Hargrave PC 13-Jun-1966
(Australia) In Western Australia, a red gum tree was struck by lightning and set on fire. The appellant had the tree cut down, but took no reasonable steps by spraying the fire with water to prevent the fire from spreading, believing that it would . .
Cited – Glasgow Corporation v Muir HL 16-Apr-1943
The House considered the proper test to define the standard of care that must be adopted by the reasonable man in a claim for negligence.
Held: Lord Clauson said that the test is whether the person owing the duty of care ‘had in contemplation . .
Cited – Bolton v Stone HL 10-May-1951
The plaintiff was injured by a prodigious and unprecedented hit of a cricket ball over a distance of 100 yards. He claimed damages in negligence.
Held: When looking at the duty of care the court should ask whether the risk was not so remote . .
Lists of cited by and citing cases may be incomplete.
Updated: 07 September 2022; Ref: scu.194897
The pursuers contracted to remove coal by opencast mining from the defender’s land. They said the contract assumed the removal first of substantial peat depositys from the surface by a third party. They had to do that themselves at substantial cost. They said the defenders should have issued a variation to allow them to claim the costs. The defenders said it could have been claimed as a quantum meruit.
Held: Quantum meruit was not normally claimable where there was a contract. There was a discretion to issue an instruction to vary and that had to be exercised reasonably. The pursuers averred that the defenders were under an obligation to ensure that their site manager operated the contract properly by issuing the instruction. No such term could be implied.
Lord Carloway
[2003] ScotCS 223
Scotland
Cited – Smith New Court Securities Ltd v Scrimgeour Vickers HL 21-Nov-1996
The defendant had made misrepresentations, inducing the claimant to enter into share transactions which he would not otherwise have entered into, and which lost money.
Held: A deceitful wrongdoer is properly liable for all actual damage . .
Cited – Downs v Chappell; Downs v Stephenson Smart (a Firm) CA 1996
The plaintiff purchased a book shop. He claimed that in doing so he had relied upon the accounts prepared and signed off by the respective defendants.
Held: The judge had been wrong by testing what would have been the true figures as against . .
Cited – Tharsis Sulpur v McElroy and Sons HL 1878
A contractor asked to carry out works was entitled to be paid on a quantum meruit basis if no price appeared to have been set under the contract. . .
Cited – Leyland and Co v Cia Panamena Europea Navigacion CA 1943
Goddard LJ said: ‘He, therefore, was unwilling to carry out the duty assigned by the contract to him. The defendants either were of the same opinion or adopted his view; for this purpose, it matters not which. Consequently, they neither required him . .
Cited – Panamena Europea Navigacion v Frederick Leyland and Co HL 1947
The parties had entered into an agreement providing for arbitration of any disputes. Lord Thankerton said: ‘By entering into the contract the respondents agreed that the appellant’s surveyor should discharge both these duties and therefore they . .
Cited – Esso Petroleum Company Ltd v Mardon CA 6-Feb-1976
Statements had been made by employees of Esso in the course of pre-contractual negotiations with Mr Mardon, the prospective tenant of a petrol station. The statements related to the potential throughput of the station. Mr Mardon was persuaded by the . .
Cited – Thorn v Mayor and Commonality of London HL 1876
The contractor successfully tendered for work involving the replacement of the existing Blackfriars Bridge pursuant to an employer’s invitation, which stated that the work was to be carried out pursuant to a specification. The specification included . .
Cited – Boyd and Forrest v Glasgow and South-Western Railway Co HL 11-Jan-1915
The issuing of an instruction was not a condition precedent to entitlement to payment in a construction contract. . .
Cited – Doyle v Olby (Ironmongers) Ltd CA 31-Jan-1969
The plaintiff had been induced by the fraudulent misrepresentation of the defendant to buy an ironmonger’s business for 4,500 pounds plus stock at a valuation of 5,000 pounds. Shortly after the purchase, he discovered the fraud and started the . .
Cited – Barry and Barry v Sutherland SCS 23-Nov-2001
The pursuers alleged that the defender had made fraudulent misrepresentations to them when selling them his bar business. On entry they had found a set of accounts showing a lower turnover, and exercised an option to break their lease.
Held: . .
Cited – South Australia Asset Management Corporation v York Montague Ltd etc HL 24-Jun-1996
Limits of Damages for Negligent Valuations
Damages for negligent valuations are limited to the foreseeable consequences of advice, and do not include losses arising from a general fall in values. Valuation is seldom an exact science, and within a band of figures valuers may differ without . .
Cited – Bank of Scotland v Dunedin Property Investment Co Ltd IHCS 24-Sep-1998
Issue of loan stock supported by charge for ‘all costs charges and expenses incurred’ this included the breakage cost of the bank in setting up interest-rate swap arrangements to protect itself against swings in costs. . .
Lists of cited by and citing cases may be incomplete.
Updated: 07 September 2022; Ref: scu.185400
Pepperall J
[2019] EWHC 989 (TCC)
England and Wales
Updated: 07 September 2022; Ref: scu.640364
UTTC Construction Industry Scheme – notices of determination – whether UK contractor obliged to make deductions under the scheme in respect of payments made to its Isle of Man parent company – FA 2004 Sections 57 to 67 – Income Tax (Construction Industry Scheme) Regulations 2005 – appeals dismissed
[2015] UKUT 472 (TCC)
England and Wales
Updated: 07 September 2022; Ref: scu.553195
Application to enforce arbitration award
Seymour QC HHJ
[2004] EWHC 3365 (QB), [2005] BLR 76, [2004] EWHC 3365 (TCC)
England and Wales
Updated: 06 September 2022; Ref: scu.431909
The builder replied to a claim in negligence that it was out of time. They had built a concrete base for a kennels. The claimant said that they had not constructed proper foundations, and that he had come to know this only within the limitation period when it began to crack.
Eder J
[2011] EWHC 838 (QB)
England and Wales
Updated: 06 September 2022; Ref: scu.431736