A construction company applied for a licence to connect a proposed supermarket site to the electricity network. It now challenged a requirement to pay the connection costs before work commenced but without allowance for interest on the early payments.
Judges:
Ouseley J
Citations:
[2017] EWHC 1175 (Admin)
Links:
Statutes:
Jurisdiction:
England and Wales
Utilities
Updated: 26 March 2022; Ref: scu.584237