The claimants owned two blocks of apartments. One contractor was unable to complete the buildings, and the defendant stepped in undertaking to complete the project within the original budget, subject to a reduction in the specifications. The owners complained that the final products were not to an acceptable standard.
Wdwards-Stuart J
[2014] EWHC 3968 (TCC)
Bailii
Contract
Updated: 24 December 2021; Ref: scu.539384