Regina v Ceredigion County Council ex parte McKeown: Admn 6 Jun 1997

The claimant sought judicial review of the grant of planning permission for a wind farm. Laws J said that it was nearly impossible to conceive of a case in which leave to move for judicial review would be granted to attack a planning permission when the application was lodged more than six weeks after the planning permission had been granted.

Judges:

Laws J

Citations:

[1997] EWHC Admin 526, [1998] 2 PLR 1, [1997] COD 463

Jurisdiction:

England and Wales

Cited by:

CitedFinn-Kelcey v Milton Keynes Council and MK Windfarm Ltd CA 10-Oct-2008
Judicial Review must be timely
The appellant challenged the grant of permission for a wind farm on neighbouring land. His application for judicial review had been rejected for delay and on the merits.
Held: The court repeated the requirement that an application must be both . .