ECJ (Judgment) Reference for a preliminary ruling – State aid – Power Purchase Agreements – Compensation paid for voluntary termination – Commission decision finding State aid compatible with the internal market – Assessment of the lawfulness of aid by a national court – Annual adjustment of stranded costs – Point at which an energy generator’s membership of a group of undertakings is taken into account

ECLI:EU:C:2016:686, [2016] EUECJ C-574/14
Bailii
European

European

Updated: 23 January 2022; Ref: scu.569377