Health and Safety Executive (Other): ICO 2 May 2018

The complainant has requested a copy of the internal investigation report carried out by Total into the blowout at the Elgin 4 Well Head in 2012. The Commissioner’s decision is that the Health and Safety Executive does not hold any further information within the scope of the request. However, in failing to inform the complainant within 20 working days that it required further time to consider the request, it breached Regulation 7(3) of the Environmental Information Regulations. The Commissioner does not require the public authority to take any further steps.
EIR 5(1): Complaint not upheld EIR 7: Complaint upheld

Citations:

[2018] UKICO fer0714017

Links:

Bailii

Jurisdiction:

England and Wales

Information

Updated: 12 November 2022; Ref: scu.617801