Arnold White Estates Ltd v National Grid Electricity Transmission Plc: UTLC 16 Apr 2013

UTLC COMPENSATION – electricity – wayleave – overhead line across housing development site – contract for sale of corridor of land containing line entered into in advance of grant of wayleave – contract conditional on removal of line – whether contract price could be taken as basis for assessment of loss – held that it could – whether land with line retained had any market value for development – held it did not – compensation pounds 5,829,476 – Electricity Act 1989 Sch 4 para 7
[2013] UKUT 5 (LC)