Appeal by a firm of architects in litigation concerning its entitlement to recover fees following termination of its engagement. The principal issue in this appeal is whether Section 111 of the 1996 Act applies only to interim payments or whether it also applies to payments due following completion of the works or termination of the contract.
Judges:
Jackson, Lindblom, Thirlwall LJJ
Citations:
[2017] EWCA Civ 1735
Links:
Statutes:
Housing Grants, Construction and Regeneration Act 1996 111
Jurisdiction:
England and Wales
Construction, Contract
Updated: 01 April 2022; Ref: scu.598471