Gotch and Another v Enelco Ltd: TCC 3 Jul 2015

Claim brought under Part 8 of the CPR for a declaration that the building contract that the Claimants entered into with the Defendant does not entitle the Defendant to refer a dispute to adjudication.

Edwards-Stuart J
[2015] EWHC 1802 (TCC), [2015] TCLR 8, [2015] 4 Costs LR 669
Bailii
England and Wales

Construction, Arbitration, Costs

Updated: 02 January 2022; Ref: scu.550211