The claimants sought damages for repudiatory breach of three contracts to construct ships.
Judges:
Burton J
Citations:
[2008] EWHC 944 (Comm), [2008] 1 CLC 816, [2008] 2 Lloyd’s Rep 202
Links:
Jurisdiction:
England and Wales
Cited by:
Appeal from – Stocznia Gdynia Sa v Gearbulk Holdings Ltd CA 13-Feb-2009
Orders were placed for the construction of ships. They were not delivered. The buyer, the defendant, cancelled the orders. The defendants sought the loss of profit. The claimants said they were entitled only to the repayment of instalments. The . .