Lord Devlin said: ‘If I employ a builder to repair my dwelling-house and he agrees to complete the work within six days or pay a penalty, that does not mean that he can keep me awake by working from midnight to midnight in order to finish the job. He can only work such hours as are reasonable or customary.’