Reference for a preliminary ruling – Internal market in natural gas – Directive 2009/73/EC – Article 2, point 3 – Concept of ‘transport’ – Article 23 – Power to decide on the connection of storage facilities, gas regasification facilities liquefied natural gas and industrial customers to the transmission network – Article 32, paragraph 1 – Access of third parties to the network – Possibility of direct connection of end customers to the natural gas transmission network
Citations:
C-290/20, [2022] EUECJ C-290/20, ECLI:EU:C:2022:119
Links:
Jurisdiction:
European
Utilities
Updated: 08 April 2022; Ref: scu.674441