Glidewell LJ stated that the cost of work to put pipes in the position contracted for would be recoverable if there was an intention to carry out the work and if it was reasonable so to do.
Judges:
Glidewell LJ
Citations:
(1987) 40 BLR 1
Cited by:
Cited – Ruxley Electronics and Construction Ltd v Forsyth HL 29-Jun-1995
Damages on Construction not as Agreed
The appellant had contracted to build a swimming pool for the respondent, but, after agreeing to alter the specification to construct it to a certain depth, in fact built it to the original lesser depth, Damages had been awarded to the house owner . .