Etablissements A. De Bloos SPRL v Societe en Commandite par Actions Bouyer: ECJ 14 Dec 1977

Europa During the period between notification and the date on which the commission takes a decision, courts before which proceedings are brought relating to an old agreement duly notified or exempted from notification must give such an agreement the legal effects attributed thereto under the law applicable to the contract, and those effects cannot be called in question by any objection which may be raised concerning its compatibility with article 85(1).

Citations:

C-59/77

European

Updated: 10 April 2022; Ref: scu.132622