Dawnus Construction Holdings v Amey Lg Ltd: TCC 26 Jan 2017

By this Part 8 claim the claimant seeks the answer to a point of construction in respect of the contract between the parties arising out of a major construction and engineering project.
[2017] EWHC B13 (TCC)
Bailii
England and Wales

Updated: 17 August 2021; Ref: scu.588993