The claimant sought payment for annual maintenance fees for the use of its software by the defendant. The defendants had said that they did not wish to renew the contract, but the notice was not in the form set out in the contract.
Held: If the notice was not given in a timely manner, another period of maintenance arose.

Judges:

Floyd J

Citations:

[2009] EWHC 97 (Ch)

Links:

Bailii

Jurisdiction:

England and Wales

Citing:

CitedInvestors Compensation Scheme Ltd v West Bromwich Building Society HL 19-Jun-1997
Account taken of circumstances wihout ambiguity
The respondent gave advice on home income plans. The individual claimants had assigned their initial claims to the scheme, but later sought also to have their mortgages in favour of the respondent set aside.
Held: Investors having once . .
Lists of cited by and citing cases may be incomplete.

Contract

Updated: 12 April 2022; Ref: scu.280427