Carillion Construction Ltd v Emcor Engineering Services Ltd and Another: CA 10 Feb 2017

Appeal by a main contractor against a decision on preliminary issues concerning delay and extension of time. The central issue is whether any extension of time granted under the standard ‘DOM/2’ form of sub-contract must commence on what was previously the due date for completion.

Judges:

Jackson, Simon, Flaux LJJ

Citations:

[2017] EWCA Civ 65

Links:

Bailii

Jurisdiction:

England and Wales

Construction