Where a contract made explicit allowance for extensions of time for performance, extensions could be granted retrospectively.
Citations:
[1952] 2 All ER 452
Cited by:
Cited – Shawton Engineering Ltd v Dgp International Ltd (T/A Design Group Partnership) and Another CA 18-Nov-2005
There had been a very substantial construction project, in which certain facets of design were sub-contracted and sub-contracted again to the parties. There were substantial delays and a sub-contractor purported to terminate the contract for failing . .