An enforcement notice was issued. The land-owner resisted, saying that the building had been substantially completed more than four years before.
Held: It was necessary only that the building works permitted by the permission should be complete, and not that the building should be complete in other ways so as to have made it habitable.
Judges:
Keene LJ
Citations:
Times 23-Oct-2001, [2000] EWHC Admin 394
Links:
Statutes:
Town and Country Planning Act 1990 171B(1)
Planning
Updated: 29 May 2022; Ref: scu.140210