Appeal by a main contractor against a decision on preliminary issues concerning delay and extension of time. The central issue is whether any extension of time granted under the standard ‘DOM/2’ form of sub-contract must commence on what was previously the due date for completion.
Judges:
Jackson, Simon, Flaux LJJ
Citations:
[2017] EWCA Civ 65
Links:
Jurisdiction:
England and Wales
Construction
Updated: 29 January 2022; Ref: scu.574292