Shropshire Council (Local Government): ICO 22 Nov 2021

The complainant requested information from Shropshire Council (‘the Council’) about documentation relating to the commissioning of a contractor for consultancy services regarding a planning application. By the date of this notice the Council had not issued a substantive response to this request. The Commissioner’s decision is that the Council has breached regulation 5(2) of the EIR in that it failed to provide a valid response to the request within the statutory time frame of 20 working days. The Commissioner requires the Council to take the following step to ensure compliance with the legislation: The Council must provide a substantive response to the request in accordance with its obligations under the EIR.
EIR 5(2): Complaint upheld

Citations:

[2021] UKICO ic-137746

Links:

Bailii

Jurisdiction:

England and Wales

Information

Updated: 07 December 2022; Ref: scu.675161