R and J Dempster Ltd v Motherwell Bridge and Engineering Co Ltd: SCS 3 Jul 1964

Although the parties had not agreed on the price which was to be mutually settled at a later date, it was held that there was a concluded contract by which the defenders were obliged to place orders with the pursuers for the steel which the pursuers had agreed to supply.

Citations:

[1964] ScotCS CSIH – 1

Links:

Bailii

Jurisdiction:

Scotland

Cited by:

CitedAvintair v Ryder Airline Services Ltd SCS 30-Dec-1993
The pursuers asserted a contract between themselves and the defenders for a consultancy, and that reasonable remuneration was due under it. The Lord Ordinary had found that no contract had been completed, the parties being, at all points, in dispute . .
Lists of cited by and citing cases may be incomplete.

Contract

Updated: 22 July 2022; Ref: scu.279469