The court was asked whether a contractor under a particular building contract was entitled to determine the contract and walk away, or whether such behaviour amounted to a repudiation entitling the main contractor to damages.
Citations:
[2008] EWCA Civ 1090
Links:
Jurisdiction:
England and Wales
Citing:
See Also – Reinwood Ltd v L Brown and Sons Ltd CA 21-Jun-2007
. .
See Also – Reinwood Ltd v L Brown and Sons Ltd HL 20-Feb-2008
The employer received a notice of non-completion from his architect, and in turn served a notice on the contractor under section 111, and deducted damages for non-completion from the next payment. The contractor said this was not allowed because the . .