Stocznia Gdynia Sa v Gearbulk Holdings Ltd: ComC 2 May 2008

The claimants sought damages for repudiatory breach of three contracts to construct ships.

Judges:

Burton J

Citations:

[2008] EWHC 944 (Comm), [2008] 1 CLC 816, [2008] 2 Lloyd’s Rep 202

Links:

Bailii

Jurisdiction:

England and Wales

Cited by:

Appeal fromStocznia Gdynia Sa v Gearbulk Holdings Ltd CA 13-Feb-2009
Orders were placed for the construction of ships. They were not delivered. The buyer, the defendant, cancelled the orders. The defendants sought the loss of profit. The claimants said they were entitled only to the repayment of instalments. The . .
Lists of cited by and citing cases may be incomplete.

Contract

Updated: 17 April 2022; Ref: scu.267419