A clause limiting an assignment to sums due and payable did not include the costs of investigation.

Citations:

Times 08-Jan-1997, [1996] EWCA Civ 1241

Jurisdiction:

England and Wales

Cited by:

See AlsoFloods of Queensferry Limited v Shand Construction Limited, Morrison Shand Limited, Morrison Construction Limited QBD 13-Feb-1997
. .