Regina v Newham London Borough Council, Ex Parte Trendgrove Properties Ltd: QBD 3 Jun 1999

A housing grant had been agreed, but when the works were not completed in time. The grant was withdrawn even though partly done. A judicial review of the decision failed because the Act had clearly imposed a requirement that works be completed within a twelve months period. No need to show bad faith.

Citations:

Gazette 03-Jun-1999

Statutes:

Housing Act 1985 189(1)

Housing

Updated: 09 April 2022; Ref: scu.85425