COMPENSATION – water – disturbance resulting from installation of water main across agricultural land – surveyor’s fee – all other surveyor’s fees in connection with the works based on Ryde’s scale (1996) plus 20 per cent – whether claimant’s surveyor entitled to a higher fee based on amount of time spent – surveyor’s fee determined on time basis at pounds 3,219.50 – Water Industry Act 1991, s159
Citations:
[2011] UKUT 84 (LC)