[1997] EWHC QB 373
Bailii
England and Wales
Citing:
See Also – Flood v Shand Construction Limited; Morrison Shand Construction Limited and Morrison Construction Limited CA 18-Dec-1996
A clause limiting an assignment to sums due and payable did not include the costs of investigation. . .
Cited by:
See Also – Floods of Queensferry Ltd, David Charles Flood v Shand Constructions Ltd, Morrison Shand Constructions Ltd, Morrison Construction Ltd TCC 17-Dec-1999
The claimant alleged that it had entered into a sub-contract relying upon misrepresentations made by the defendant, SCL that it was the main contractor, and that it was still trading. The defendant company operated through associated companies for . .
Lists of cited by and citing cases may be incomplete.
Updated: 21 July 2021; Ref: scu.135928 br>