Davis J
[2009] EWHC 852 (Ch), [2009] 2 Lloyds Rep 246, [2009] 2 All ER (Comm) 1083
Bailii
England and Wales
Cited by:
Appeal from – Durham Tees Valley Airport Ltd v BMIbaby Ltd and Another CA 5-May-2010
Whilst it is correct that damages for breach of contract are assessed on the basis that the party in breach would have performed the contract in the manner least onerous to it, the court will make its counterfactual assessment on the basis that the . .