The complainant has requested information concerning the cost benefit analysis of advanced (energy) meters carried out by the former Department for Business, Enterprise and Regulatory Reform (now the Department for Business, Energy and Industrial Strategy). BEIS refused the original request in its entirely and a subsequent refined request in part under Section 12 (costs limit of the FOIA and/or Regulation 12(4)(b)(manifestly unreasonable). The Commissioner’s decision is that BEIS correctly refused both requests as manifestly unreasonable and that the public interest balance favours maintaining the exception in both cases. However, the Commissioner has found that BEIS breached Regulations 5(2) and 11(4) in their handling of the requests.
EIR 12(4)(b): Complaint not upheld