Byrne and Byrne v Hall Pain and Foster (a Firm) and others: CA 11 Dec 1998

The cause of action in an action for professional negligence in purchase of land ran from the date of exchange of contracts not completion, and the limitation period was to be calculated accordingly.
Simon Brown, Otton, Schiemann LJJ
Times 08-Jan-1999, Gazette 03-Feb-1999, [1998] EWCA Civ 1939, [1999] 1 WLR 1849, [1999] PNLR 565
Bailii
Limitation Act 1980
England and Wales