Ballast Plc v The Burrell Company (Construction Management) Limited: SCS 21 Jun 2001

In a building dispute, the arbitrator found that the parties had departed from the standard JCT terms, and declined to arbitrate. The parties said that when called upon to act he ‘shall’ do so. The adjudicator had misconstrued his powers. It was clear that there was a proper dispute requiring his decision, and he was … Continue reading Ballast Plc v The Burrell Company (Construction Management) Limited: SCS 21 Jun 2001