Regina v London Borough of Hammersmith and Fulham And Others, ex parte Burkett and Another: HL 23 May 2002

The applicant sought judicial review of the respondent’s grant of planning permission for a development which would affect her. The authority objected that the application was made after three months after their decision, and so leave should not be granted, and also that her application for leave having been refused, there was no jurisdiction in … Continue reading Regina v London Borough of Hammersmith and Fulham And Others, ex parte Burkett and Another: HL 23 May 2002

Finn-Kelcey v Milton Keynes Council and MK Windfarm Ltd: CA 10 Oct 2008

Judicial Review must be timely The appellant challenged the grant of permission for a wind farm on neighbouring land. His application for judicial review had been rejected for delay and on the merits. Held: The court repeated the requirement that an application must be both timely and in any event made within three months. Both … Continue reading Finn-Kelcey v Milton Keynes Council and MK Windfarm Ltd: CA 10 Oct 2008

Hardy and others v Pembrokeshire County Council and Another: CA 19 Jul 2006

The court considered the consequences of delay in applications for judicial review: ‘It is important that those parties, and indeed the public generally, should be able to proceed on the basis that the decision is valid and can be relied on, and that they can plan their lives and make personal and business decisions accordingly.’ … Continue reading Hardy and others v Pembrokeshire County Council and Another: CA 19 Jul 2006